Which of the following is NOT a principle of managing bottlenecks?
A) a time buffer should be established after each bottleneck
B) the rate of material fed to a bottleneck should be controlled
C) do anything to increase the capacity of a bottleneck
D) use alternate routings
E) change the schedule
Correct Answer:
Verified
Q25: Given the following information, which sequence
Q26: The planned backlog was:
A) 30
B) 36
C) 40
D)
Q27: The selection and sequencing of available jobs
Q28: In a drum-buffer-rope scheduling system, the "drum"
Q29: If today is manufacturing day 100 and
Q30: Which of the following is concerned with
Q31: Operation splitting means:
A) the same job running
Q32: The following information is to be used
Q33: A scheduling system that assumes the required
Q35: Operation overlapping means:
A) using alternate routings
B) moving
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents