Lark Corp.has a contract to construct a $5,000,000 cruise ship at an estimated cost of $4,000,000.The company will begin construction of the cruise ship in early January 2011 and expects to complete the project sometime in late 2014.Lark Corp.has never constructed a cruise ship before, and the customer has never operated a cruise ship.Due to this and other circumstances, Lark Corp.believes there are inherent hazards in the contract beyond the normal, recurring business risks.Lark Corp.expects to recover all its costs under the contract.During 2011 and 2012, the company has the following activity:
For the year ended December 31, 2012, how much revenue should Lark Corp.recognize on its income statement?
A) $980,000
B) $2,040,000
C) $1,300,000
D) $1,060,000
Correct Answer:
Verified
Q61: The following information relates to questions
Q62: Wynn, Inc.has a contract to construct a
Q63: Use the following information for questions.
Gorman Construction
Q64: Use the following information for questions.
Kiner, Inc.began
Q65: Use the following information for questions.
Eilert Construction
Q67: The following information relates to questions
Q68: Lark Corp.has a contract to construct a
Q69: Remington Construction Company uses the percentage-of-completion method.During
Q70: Use the following information for questions.
Gomez, Inc.began
Q71: Use the following information for questions.
Gorman Construction
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents