Question 23

Multiple Choice

A flexible budget


A) is not as useful in evaluating a manager's performance as a static budget.
B) can be prepared for each of the types of budgets included in the master budget.
C) relies on the assumption that unit fixed costs will remain constant within the relevant range of activity.
D) reflects budget data for one level of activity only.