Use the following information for questions 83 and 84.
Eilert Construction Company had a contract starting April 2015, to construct a $21,000,000 building that is expected to be completed in September 2016, at an estimated cost of $19,250,000. At the end of 2015, the costs to date were $8,855,000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $4,200,000 and the cash collected during 2015 was $2,800,000. Eilert uses the percentage-of-completion method.
-For the year ended December 31, 2015, Eilert would recognize gross profit on the building of
A) $0.
B) $737,917.
C) $805,000.
D) $945,000.
Correct Answer:
Verified
Q90: Use the following information for questions 96-98.
During
Q91: Fryman Furniture uses the installment-sales method. No
Q92: Oliver Co. uses the installment-sales method to
Q93: Melton Company sold some machinery to Addison
Q94: Use the following information for questions 80
Q96: Spicer Corporation has a normal gross profit
Q97: Use the following information for questions 99
Q98: Remington Construction Company uses the percentage-of-completion method.
Q99: Use the following information for questions 86
Q100: Carperter Company has used the installment
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents