Use the following information for questions 65-68:
Seasons Construction is constructing an office building under contract for Cannon Company. The contract calls for progress billings and payments of $1,240,000 each quarter. The total contract price is $14,880,000 and Seasons estimates total costs of $14,200,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2014.
-At December 31, 2014, Seasons estimates that it is 30% complete with the construction, based on costs incurred. What is the total amount of Revenue from Long-Term Contracts recognized for 2014 and what is the balance in the Accounts Receivable account assuming Cannon Cafe has not yet made its last quarterly payment?
Correct Answer:
Verified
Q75: Monroe Construction Company uses the percentage-of-completion method
Q76: Use the following information for questions 65-68:
Seasons
Q77: Use the following information for questions 76
Q78: Use the following information for questions 65-68:
Seasons
Q79: Use the following information for questions 80
Q81: Sutton Company sells plasma-screen televisions on an
Q82: Daily, Inc. appropriately used the installment method
Q83: Hiser Builders, Inc. is using the
Q84: Use the following information for questions 99
Q85: Use the following information for questions 83
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents