In Microsoft Project, the correct sequence of defining a project's working time is:
A) select calendar template, manipulate days of the week, specify number of hours per day, specify non- working time, and verify calendar.
B) select calendar template, specify non- working time, manipulate days of the week, specify number of hours per day, and verify calendar.
C) select calendar template, specify non- working time, specify number of hours per day, manipulate days of the week, and verify calendar.
D) select calendar template, manipulate days of the week, specify non- working time, specify number of hours per day, and verify calendar.
Correct Answer:
Verified
Q13: A red bar in the resource graph
Q14: What is NOT an option for assigning
Q15: What is NOT among the options for
Q16: The_ is a toolbar that includes
Q17: The fastest method of tracking progress in
Q19: A moderately time- consuming method of tracking
Q20: The resource graph view shows the:
A)percent of
Q21: Microsoft Project calculates schedules based on_
Q22: You can choose between all four task
Q23: "Always track by entering the actual work
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents