A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called:
A) critical path method.
B) OPR method.
C) program evaluation and review technique.
D) expected completion time analysis.
Correct Answer:
Verified
Q34: A set of procedures used by organizations
Q35: What is NOT unique about IT projects?
A)Extensive
Q36: There are _ major project management process
Q37: The Project Management Body of Knowledge contains
Q38: The Gantt chart was developed:
A)during the Manhattan
Q40: IT project teams can include:
A)end users.
B)systems analysts.
C)programmers.
D)all
Q41: A technique that uses optimistic, pessimistic, and
Q42: Increases in project scope are_ for IT
Q43: The project management core area including quality
Q44: A diagram that shows the ordering of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents