_________Are Documented and Authorized Guidelines Necessary to Bring Future Project

Question 40

Multiple Choice

_________are documented and authorized guidelines necessary to bring future project performance in conformance with the project management plan.


A) Approved preventive actions
B) Approved change requests
C) Approved defect repair
D) Approved corrective actions

Correct Answer: