The_________ is calculated by dividing the original time estimate by the SPI.
A) estimated time to complete
B) completion time
C) estimated cost at completion
D) schedule performance index
Correct Answer:
Verified
Q23: A post- implementation review is conducted:
A)a few
Q24: A_ is a systematic and formal enquiry
Q25: _are approved and authorized actions that are
Q26: _is the difference between the scheduled completion
Q27: A cost control method for examining project
Q29: Project control is the process of monitoring
Q30: _is the difference between the earned value
Q31: _are activities and reporting methods instituted during
Q32: Reluctance to hear bad news communicated from
Q33: A(n)_contains a record of the project management