The amount of time an activity can be delayed without delaying the project is called:
A) delay time.
B) lag time.
C) slack time.
D) free time.
Correct Answer:
Verified
Q44: Problem solving consists of:
A)problem analysis and solution
Q45: The review points at the end of
Q46: A _is a series of continuous actions
Q47: The third phase in the SDLC is
Q48: The shortest time in which a project
Q50: The process group concerned with authorizing a
Q51: The amount if time a task can
Q52: The technique that uses optimistic, pessimistic, and
Q53: The five process groups identified by the
Q54: Projects are divided into smaller parts called