The use of mathematical techniques to shorten a project's duration is called:
A) schedule compression.
B) crashing.
C) PERT.
D) fast- tracking.
Correct Answer:
Verified
Q32: _ is the process of estimating
Q33: Resource allocation:
A)plays a large role in determining
Q34: The longest path through a network diagram
Q35: The process of determining start and finish
Q36: _ is an estimating technique in
Q38: The performance of activities in parallel that
Q39: _ is the measure of the
Q40: The process of putting procedures and rules
Q41: _ slack is the time and
Q42: The prudent project manager should provide