What is the float start time for Activity C given the activity times and precedence requirements shown in the table? 
A) 1
B) 2
C) 3
D) 4
Correct Answer:
Verified
Q87: Float is always measured in exactly the
Q93: Q94: An MBA student laboriously calculated the early Q95: Use the values in the table to Q96: Use the information in the table to Q100: Use the values in the table to Q102: Which technique would accelerate the completion of Q103: In general,the better candidates for shortening are: Q104: What is laddering and what advantages can Q105: Discuss any five approaches to reducing the![]()