Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by one day what is the total time of the project and total cost?
A) Total time is 13 days, total cost is $1500
B) Total time is 12 days, total cost is $2000
C) Total time is 12 days, total cost is $2300
D) Total time is 11 days, total cost is $1850
E) Total time is 11 days, total cost is $2350
Correct Answer:
Verified
Q64: In a project analysis using three time
Q65: You have just used the network planning
Q67: Below are the data for a Time-Cost
Q67: You have just performed a CPM analysis
Q68: You have the following time and cost
Q70: You have just used the network planning
Q71: Below are the data for a Time-Cost
Q72: You have collected the data for a
Q73: The major goal of critical path analysis
Q74: What does "EVM" stand for?
A) Extra Value
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents