Task C is directly preceded by two tasks-task A and task B.Task A has an expected task completion time of five weeks and an ES time of week 6.Task B has an expected task completion time of seven weeks and an ES time of week 7.Task C has an expected task completion time of 10 weeks.The ES for activity C is week
A) 7.
B) 14.
C) 12.
D) 24.
Correct Answer:
Verified
Q37: Performing the work necessary to complete the
Q38: The project planning step of estimating activity
Q39: The act of leading and directing the
Q40: People that are dispersed around the country
Q41: A tool for prioritizing potential projects where
Q43: In a project network,the critical path is
Q44: Key phases in a project time line
Q45: Following are the three time estimates for
Q46: Key phases in a project time line
Q47: The shortest time for completing a project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents