One of the three types of MRP action notices possible is releasing a new order.Which one of the following statements is TRUE about releasing a new order?
A) Release an order when there is a nonzero quantity in the first period's planned order release row.
B) Release a separate order for service parts.
C) Release an order when there is a nonzero quantity in the scheduled receipt row.
D) Release an order when the first period's gross requirements quantity is equal to zero.
Correct Answer:
Verified
Q53: If a planned receipt for an item
Q62: Which one of the following statements concerning
Q63: The underlying logic for level-by-level processing in
Q64: Which one of the following is an
Q65: The action notice is a
A) document that
Q66: Which one of the following statements about
Q69: MRP explosion means estimating the total number
Q70: The purpose of Finite Capacity Scheduling is
Q71: Which of the following statements about MRP
Q72: Which of the following statements about Enterprise
Unlock this Answer For Free Now!