Solved

Conversion Factors for the Cumulative Average Number of Direct Labor

Question 21

Multiple Choice

Conversion Factors for the Cumulative Average Number of Direct Labor Hours per Unit
80% Learning Rate  ( n= cumulative production)  nnn11.00000190.53718370.4397620.90000200.52425380.4363430.83403210.51715390.4330440.78553220.51045400.4298450.74755230.50410640.3738260.71657240.498081280.3026970.69056250.492342560.2440580.66824260.486885120.1962290.64876270.481676000.18661100.63154280.476687000.17771110.61613290.471918000.17034120.60224300.467339000.16408130.58960310.462931,0000.15867140.57802320.458711,2000.14972150.56737330.464641,4000.14254160.55751340.450721,6000.13660170.54834350.446941,8000.13155180.53979360.443292,0000.1272090% Learning Rate  ( n= cumulative production)  nnn11.00000190.73545370.6709120.95000200.73039380.6683930.91540210.72559390.6659540.88905220.72102400.6635750.86784230.71666640.6204360.85013240.712511280.5606970.83496250.708532560.5058680.82172260.704725120.4559490.80998270.701066000.44519100.79945280.697547000.43496110.78991290.694168000.42629120.78120300.690909000.41878130.77320310.687751,0000.41217140.76580320.674711,2000.40097150.75891330.681771,4000.39173160.75249340.678931,6000.38390170.74646350.676171,8000.37711180.74080360.673502,0000.37114\begin{array}{c}\begin{array}{c}80 \% \text { Learning Rate }\\\text { ( } n=\text { cumulative production) }\\\begin{array}{rrrrrr}\hline n & & n & & {n} & \\\hline 1 & 1.00000 & 19 & 0.53718 & 37 & 0.43976 \\2 & 0.90000 & 20 & 0.52425 & 38 & 0.43634 \\3 & 0.83403 & 21 & 0.51715 & 39 & 0.43304 \\4 & 0.78553 & 22 & 0.51045 & 40 & 0.42984 \\5 & 0.74755 & 23 & 0.50410 & 64 & 0.37382 \\6 & 0.71657 & 24 & 0.49808 & 128 & 0.30269 \\7 & 0.69056 & 25 & 0.49234 & 256 & 0.24405 \\8 & 0.66824 & 26 & 0.48688 & 512 & 0.19622 \\9 & 0.64876 & 27 & 0.48167 & 600 & 0.18661 \\10 & 0.63154 & 28 & 0.47668 & 700 & 0.17771 \\11 & 0.61613 & 29 & 0.47191 & 800 & 0.17034 \\12 & 0.60224 & 30 & 0.46733 & 900 & 0.16408 \\13 & 0.58960 & 31 & 0.46293 & 1,000 & 0.15867 \\14 & 0.57802 & 32 & 0.45871 & 1,200 & 0.14972 \\15 & 0.56737 & 33 & 0.46464 & 1,400 & 0.14254 \\16 & 0.55751 & 34 & 0.45072 & 1,600 & 0.13660 \\17 & 0.54834 & 35 & 0.44694 & 1,800 & 0.13155\\18& 0.53979 & 36 & 0.44329 & 2,000 & 0.12720\end{array}\end{array}\begin{array}{cl}90 \% \text { Learning Rate }\\\text { ( } n=\text { cumulative production) }\\\begin{array}{rrrrrr}\hline n &&{n} & &n & \\\hline 1 & 1.00000 & 19 & 0.73545 & 37 & 0.67091 \\2 & 0.95000 & 20 & 0.73039 & 38 & 0.66839 \\3 & 0.91540 & 21 & 0.72559 & 39 & 0.66595 \\4 & 0.88905 & 22 & 0.72102 & 40 & 0.66357 \\5 & 0.86784 & 23 & 0.71666 & 64 & 0.62043 \\6 & 0.85013 & 24 & 0.71251 & 128 & 0.56069 \\7 & 0.83496 & 25 & 0.70853 & 256 & 0.50586 \\8 & 0.82172 & 26 & 0.70472 & 512 & 0.45594 \\9 & 0.80998 & 27 & 0.70106 & 600 & 0.44519 \\10 & 0.79945 & 28 & 0.69754 & 700 & 0.43496 \\11 & 0.78991 & 29 & 0.69416 & 800 & 0.42629 \\12 & 0.78120 & 30 & 0.69090 & 900 & 0.41878 \\13 & 0.77320 & 31 & 0.68775 & 1,000 & 0.41217 \\14 & 0.76580 & 32 & 0.67471 & 1,200 & 0.40097 \\15 & 0.75891 & 33 & 0.68177 & 1,400 & 0.39173 \\16 & 0.75249 & 34 & 0.67893 & 1,600 & 0.38390 \\17 & 0.74646 & 35 & 0.67617 & 1,800 & 0.37711 \\18 & 0.74080 & 36 & 0.67350 & 2,000 & 0.37114\end{array}\end{array}\end{array}

-Given that the fifth unit took 10 hours to build and the learning rate is 90 percent,how much time will it take to build units 11 through 15? Refer to the copy of Table G.1 above.


A) Fewer than or equal to 38 hours
B) Greater than 38 hours but fewer than or equal to 40 hours
C) Greater than 40 hours but fewer than or equal to 42 hours
D) Greater than 42 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents