In a BPMN activity diagram,which of the following represent a valid use for an intermediate timer event?
A) Represent a time delay
B) Indicates a delay to a specific date/time
C) Indicates a delay to a relative date,such as next Thursday
D) All of these choices are correct
Correct Answer: