Solved

A Simple Sequential Project (Each Task Must Be Completed Before

Question 2

Multiple Choice

A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below: A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:   What is the probability that the project will be completed within 8.5 days? (Choose the closest answer.)  A) 80 percent B) 15 percent C) 75 percent D) 5 percent What is the probability that the project will be completed within 8.5 days? (Choose the closest answer.)


A) 80 percent
B) 15 percent
C) 75 percent
D) 5 percent