A construction contractor entered into a contract to build a family room addition onto Harry's home for $25,000.In order to encourage timely performance,the agreement provided that the contractor would be penalized $5,000 as liquidated damages for each day that the project was late in getting finished.The contractor was 30 days late in finishing the project,but otherwise met the terms of the agreement.What is most likely in this situation?
A) The liquidated damages clause would not be enforced due to its being excessive.
B) The liquidated damages clause would be limited to $25,000, the amount of the contract price.
C) The liquidated damages clause would be enforced.
D) The liquidated damages clause would not be enforced because the parties made a mutual mistake about when the contract would be finished.
E) The liquidated damages clause would be enforced only if it can be shown that the contractor has made that much in profits over the past six months.
Correct Answer:
Verified
Q124: Billy Bob had a great job handling
Q125: What is required in order for a
Q126: Liquidated damages clauses will generally not be
Q127: Henry took his Porsche to the shop
Q128: Should there be such a tort as
Q130: Specific performance is generally awarded:
A) in cases
Q131: Justin purchased a new Ford Thunderbird in
Q132: Pat Painter contracts to paint Harry Homeowner's
Q133: Creative Charlie had sketched plans for an
Q134: Bob is moving to another job across
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents