The general requirements for a liquidated damages clause to be enforceable are that:
A) actual damages are difficult to determine and the liquidated damages amount is reasonable.
B) actual damages exceed the amount foreseen by the parties.
C) the liquidated damages clause applies only to unforeseeable damages.
D) the breaching party used its best efforts to avoid a breach of the contract.
E) the parties have rescinded the contract.
Correct Answer:
Verified
Q103: In connection with a contract,what is rescission?
A)
Q104: If an employer breaches an employment contract,the
Q105: The term "mitigation" refers to the _
Q106: In Hickman v.Bates,involving the sale of land
Q107: Damages that are fixed in the contract
Q109: What does the term "mitigation" refer to
Q110: In Alba v.Kauffman,the court ruled that specific
Q111: _ damages are usually awarded in a
Q112: When,generally,are equitable remedies available?
A) They are usually
Q113: Which of the following types of damages
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents