The budget was tight when the project entered the testing phase so Bob decided to implement the ________ for the new system. It was a disaster because the customer service agents could not log in to their accounts. So the testing team had to come and reinstall the old system.


A) plunge installation method
B) parallel installation method
C) pilot installation method
D) phased installation method