Raul Was Leading a Team Charged with Developing a New

Question 24

Multiple Choice

Raul was leading a team charged with developing a new system for budgeting.Which of the following questions is best paired with the most appropriate phase of the systems development life cycle?


A) Initiation/planning: Should we use Excel or some other information technology tool?
B) Requirements analysis: Should we use Excel or some other information technology tool?
C) Requirements analysis: What goals should the new budgeting system achieve?
D) Initiation/planning: How many people should be on the team?

Correct Answer: