Question 33

Multiple Choice

Raul was leading a team charged with developing a new system for budgeting.If he decides to use the systems development life cycle, which of the following questions would he most likely ask during its second step?


A) Do we really need a new budgeting system?
B) How many people should be on the team?
C) What goals should the new budgeting system achieve?
D) Should we use Excel or some other information technology tool?

Correct Answer:

verifed

Verified