An AOA network:
A) cannot show a merge activity.
B) cannot show a burst activity.
C) cannot have consecutive merge and burst activities.
D) can have all of the features described in A-C above.
Correct Answer:
Verified
Q56: What is project crashing and what are
Q82: Crashing costs for a project are governed
Q83: A project manager ascertained that five different
Q84: Use the information in the table to
Q85: Research has shown that,in general:
A)there is a
Q86: AON networks have an advantage over AOA
Q88: Networks would not be well suited for:
A)planning
Q89: What is the duration of the project
Q90: A complex project that is managed using
Q91: What is the cost to finish this