A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project?
A) $222,667
B) $217,000
C) $222,000
D) $208,000
Correct Answer:
Verified
Q62: What is the late finish for activity
Q63: An activity on an arrow network:
A)cannot have
Q64: Use the information in the table (all
Q65: It costs $75 per day for each
Q66: A project has the activity duration and
Q68: Dummy activities have a duration equal to
Q69: A project has the activity duration and
Q70: The critical path of this network is:
Q71: Use the information in the table (all
Q72: The fastest completion time for this project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents