A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer if this project is managed using critical chain methodology?
A) 9.0
B) 7.5
C) 4.5
D) 6.0
Correct Answer:
Verified
Q47: Your next project consists of 10 consecutive
Q57: All five members of a project team
Q58: If a project activity experiences positive variation:
A)the
Q59: A worker is assigned three tasks,A,B,and C,each
Q60: All five members of a project team
Q61: A project consists of three activities with
Q63: A project consists of four consecutive tasks
Q64: A project is represented by the activity
Q66: CCPM advocates performing all non-critical activities:
A)as late
Q67: A project consists of six consecutive tasks
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents