At the end of week 20,this project has cost $79,000 and has an earned value as indicated in the table.Use the data to calculate the cost performance index for the project.All amounts are in thousands of dollars.
A) 1.11
B) 0.82
C) 0.94
D) 0.90
Correct Answer:
Verified
Q62: Use the data to calculate the earned
Q63: Use the data to calculate the earned
Q64: At the end of week 10,this project
Q65: Use the earned value table to determine
Q66: Use the data to calculate the schedule
Q68: The first step in earned value management
Q69: Use the earned value table for Project
Q70: Use the data to calculate the earned
Q71: In earned value management analysis,the cumulative amount
Q72: Use the earned value table to determine