Marilyn Contracted with Bravo Builders to Build an Addition to Her

Question 43

Multiple Choice

Marilyn contracted with Bravo Builders to build an addition to her house for $15,000.After digging the foundation,Bravo decides that it will take more work and more concrete than it had originally thought and that it will need to charge an additional $5,000 for the job.Assuming Marilyn agrees,which of the following is correct?


A) Marilyn will have to pay $20,000.
B) This is a contract under seal which is enforceable.
C) This is a modification of a preexisting contract,which under common law must be supported by additional consideration on the part of Bravo Builders.
D) This is the settlement of a disputed debt that requires no additional consideration on the part of Bravo Builders.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents