In the Analytical Approach,the Probabilities of Completing the Project Within

Question 78

Multiple Choice

In the analytical approach,the probabilities of completing the project within a certain time are computed assuming that ________.


A) the expected project completion time is the product of the expected activity times along the critical path,which is found using the expected activity times
B) the variance of the distribution is the sum of the variances of those activities along the critical path,which is found using the expected activity times
C) the variance of the distribution is the sum of the variances of those activities along the critical path,which is found using the variances of activity times
D) the distribution of project completion times is not known

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents