The Three Main Inputs of a Material Requirements Planning (MRP)system

Question 5

Multiple Choice

The three main inputs of a material requirements planning (MRP) system are:


A) required human resources,machine resources,and available resources.
B) required manufacturing resources,human resources,and master production schedule.
C) inventory records,annual sales forecast,and a master production schedule.
D) Pareto analysis results,inventory records,and a master production schedule.
E) bill of material,a master production schedule,and the inventory record.