Table 11-2
The following represents a project with four activities.All times are in weeks.
-According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer,it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?
A) 2
B) 4
C) 8
D) 12
E) None of the above
Correct Answer:
Verified
Q57: Given an activity's optimistic,most likely,and pessimistic time
Q58: Table 11-1
The following represents a project with
Q59: Using the data in Table 11-1,compute the
Q60: CPM
A)assumes we do not know ahead of
Q61: Consider a project that has an expected
Q63: Table 11-3 Q64: The critical path of a network is Q65: Your company is considering submitting a bid Q66: Table 11-3 Q67: Table 11-2
The following represents a project with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents