Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.
A) day 5
B) day 3
C) day 7
D) Cannot be calculated based upon information given.
Correct Answer:
Verified
Q53: With projects for which there is a
Q54: Earliest finish time (EF)is the earliest time
Q55: Calculate the latest finish for Task B
Q56: Total slack for the project is the
Q57: Calculate the earliest start for Task B
Q59: Earliest start time (ES)is the earliest time
Q60: Calculate the earliest finish for Task B
Q61: Free slack is calculated by finding the
Q62: Analyzing the schedule to determine which areas
Q63: The total completion time is 25 days.Task
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents