The Cumulative Budgeted Cost Is

Question 91

Multiple Choice

The cumulative budgeted cost is


A) the aggregate estimated costs of all the activities.
B) the amount budgeted to accomplish the work scheduled to a point in time in the project.
C) the committed costs for an activity.
D) the sum of all the funds expended to a point in time in the project.

Correct Answer: