Risks ____ should be given higher priority because if the risk occurs, it would have a greater impact on the schedule than if it was associated with activities on a path that has a large positive value of total slack.
A) that occur first in the project
B) that affect the most costly activities
C) on the critical path
D) that affect the activities near the end of the project
Correct Answer:
Verified
Q16: _ involves identifying, assessing, and responding to
Q17: The project team can progressively elaborate and
Q18: A risk is an uncertain event that,
Q19: Risk identification is determining which risks may
Q20: The project manager needs to set the
Q22: If the risks seem _, the contractor
Q23: Risks are prioritized based on
A) the likelihood
Q24: _ can be to avoid the risk,
Q25: A common approach to identifying the sources
Q26: _ contains the steps for how to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents