Activity D of a project has a budgeted cost of $45,000 and is 20% complete.What is the value of work completed?
A) 450
B) 4500
C) 900
D) 9000
Correct Answer:
Verified
Q95: Figure 11-1 Q96: Figure 11-1 Q97: PERT assumes that the total completion time Q98: Table 11-5 Q99: The crash time of an activity represents Q101: Table 11-7 Q102: Table 11-8 Q103: Table 11-8 Q104: Table 11-8 Q105: Table 11-8 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents