The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J=6. a. What task must be on the critical path, regardless of activity durations?
b. What is the duration of path A-B-E-H-J?
c. What is the critical path of this network?
d. What is the length of the critical path?
e. What is slack time at activity H?
f. What is the Late Finish of activity H?
g. If activity C were delayed by two time units, what would happen to the project duration?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q66: What are the earliest activity start time
Q111: PERT calculations typically include the duration variance
Q112: A network consists of the activities in
Q113: A partially solved PERT problem is detailed
Q114: Given the project within the table below
Q115: Draw the AOA and AON networks for
Q116: Three critical path activities are candidates for
Q120: A network consists of the following list.
Q121: Consider the network presented in the following
Q122: Pirmin's Bike Shop is behind on a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents