Which of the following is FALSE with respect to resource estimation activity?
A) This information is used to create a project resource plan.
B) Project managers use a variety of tools to assist in making estimates of project size and costs.The most widely used method is called COCOMO.
C) Resource estimates may need not be revised based upon the skills of the actual person (or people) assigned to a particular activity.
D) People are the most important,and expensive,part of project resource planning.
Correct Answer:
Verified
Q27: How many activities are involved in the
Q28: What is the next step taken after
Q29: Which of the following is FALSE with
Q30: A Gantt chart is the graphical representation
Q31: Which of the following is NOT true
Q33: Resource estimates may need to be revised
Q34: The distinguishing feature of a network diagram
Q35: Which of the following is NOT true
Q36: During _,the project manager performs several activities
Q37: Which of the following is a FALSE
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents