Multiple Choice
In a PERT/CPM chart, each task has all of the following EXCEPT a(n) ____.
A) reference to successor tasks
B) ID
C) name
D) duration
Correct Answer:
Verified
Related Questions
Q1: Q2: A _ might involve maximums for one Q7: Project scheduling involves all of the following Q8: The first step in creating a WBS Q10: Many project managers find _ charts more Q11: A task is any work that requires Q15: A _ path includes all tasks that Q17: In addition to tasks, every project has Q18: PERT/CPM is called a(n) _ technique, because Q19: The first step in the creation of