The process groups are linked to each other by the ________ they produce.
A) inputs
B) products
C) services
D) outputs
Correct Answer:
Verified
Q47: The Executing processes coordinate all _ during
Q48: The Planning processes ensure that the _
Q49: In an iterative project, each _ consists
Q50: The project management process groups consist of
Q51: The PMBOK establishes a common _ to
Q53: The _ processes monitor project variances from
Q54: Organizations use the PMBOK as a starting
Q55: The Project Management Institute is an international
Q56: PMI refers to Initiating, Planning, Executing, Controlling,
Q57: The Initiating processes _ the beginning or