Deck 26: Investment Return and Risk Analysis Questions

ملء الشاشة (f)
exit full mode
سؤال
Exhibit 1A.1
 Probability  Rate of Return .15.10.15.20.35.00.25.15.10.15\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .15 & - .10 \\.15 & - .20 \\.35 & .00 \\.25 & .15 \\.10 & .15\end{array}

-Refer to Exhibit 1A.1.The standard deviation of your expected return from this investment is

A) 0.001
B) 0.004
C) 0.124
D) 1.240
E) None of the above
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Exhibit 1A.2
Use the Information Below for the Following Problem(S)
You have an opportunity to invest in project X with the following expected rates of return:
 Probability  Rate of Return .25.10.25.00.50.10\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .25 & - .10 \\.25 & .00 \\.50 & .10\end{array}

-Refer to Exhibit 1A.2.The expected return for project X is

A) 0.0 percent
B) 0.5 percent
C) 2.5 percent
D) 5.0 percent
E) 7.5 percent
سؤال
An investment has a standard deviation of 12 percent and an expected return of 7 percent.What is the coefficient of variation for this investment?

A) 1.714
B) 1.372
C) 0.714
D) 0.583
E) 0.500
سؤال
Exhibit 1A.1
 Probability  Rate of Return .15.10.15.20.35.00.25.15.10.15\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .15 & - .10 \\.15 & - .20 \\.35 & .00 \\.25 & .15 \\.10 & .15\end{array}

-Refer to Exhibit 1A.1.The expected return from this investment is

A) -0.0752
B) -0.0040
C) 0.00
D) 0.0075
E) 0.4545
سؤال
Exhibit 1A.1
 Probability  Rate of Return .15.10.15.20.35.00.25.15.10.15\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .15 & - .10 \\.15 & - .20 \\.35 & .00 \\.25 & .15 \\.10 & .15\end{array}

-Refer to Exhibit 1A.1.The coefficient of variation of this investment is

A) -0.06
B) -0.65
C) 6.60
D) 16.53
E) 165.10
سؤال
Exhibit 1A.2
Use the Information Below for the Following Problem(S)
You have an opportunity to invest in project X with the following expected rates of return:
 Probability  Rate of Return .25.10.25.00.50.10\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .25 & - .10 \\.25 & .00 \\.50 & .10\end{array}

-Refer to Exhibit 1A.2.The standard deviation for project X is

A) -1.581 percent
B) 0.000 percent
C) 1.581 percent
D) 2.738 percent
E) 5.000 percent
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/6
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 26: Investment Return and Risk Analysis Questions
1
Exhibit 1A.1
 Probability  Rate of Return .15.10.15.20.35.00.25.15.10.15\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .15 & - .10 \\.15 & - .20 \\.35 & .00 \\.25 & .15 \\.10 & .15\end{array}

-Refer to Exhibit 1A.1.The standard deviation of your expected return from this investment is

A) 0.001
B) 0.004
C) 0.124
D) 1.240
E) None of the above
0.124
2
Exhibit 1A.2
Use the Information Below for the Following Problem(S)
You have an opportunity to invest in project X with the following expected rates of return:
 Probability  Rate of Return .25.10.25.00.50.10\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .25 & - .10 \\.25 & .00 \\.50 & .10\end{array}

-Refer to Exhibit 1A.2.The expected return for project X is

A) 0.0 percent
B) 0.5 percent
C) 2.5 percent
D) 5.0 percent
E) 7.5 percent
2.5 percent
3
An investment has a standard deviation of 12 percent and an expected return of 7 percent.What is the coefficient of variation for this investment?

A) 1.714
B) 1.372
C) 0.714
D) 0.583
E) 0.500
1.714
4
Exhibit 1A.1
 Probability  Rate of Return .15.10.15.20.35.00.25.15.10.15\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .15 & - .10 \\.15 & - .20 \\.35 & .00 \\.25 & .15 \\.10 & .15\end{array}

-Refer to Exhibit 1A.1.The expected return from this investment is

A) -0.0752
B) -0.0040
C) 0.00
D) 0.0075
E) 0.4545
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 6 في هذه المجموعة.
فتح الحزمة
k this deck
5
Exhibit 1A.1
 Probability  Rate of Return .15.10.15.20.35.00.25.15.10.15\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .15 & - .10 \\.15 & - .20 \\.35 & .00 \\.25 & .15 \\.10 & .15\end{array}

-Refer to Exhibit 1A.1.The coefficient of variation of this investment is

A) -0.06
B) -0.65
C) 6.60
D) 16.53
E) 165.10
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 6 في هذه المجموعة.
فتح الحزمة
k this deck
6
Exhibit 1A.2
Use the Information Below for the Following Problem(S)
You have an opportunity to invest in project X with the following expected rates of return:
 Probability  Rate of Return .25.10.25.00.50.10\begin{array} { c c } \text { Probability } & \text { Rate of Return } \\\hline .25 & - .10 \\.25 & .00 \\.50 & .10\end{array}

-Refer to Exhibit 1A.2.The standard deviation for project X is

A) -1.581 percent
B) 0.000 percent
C) 1.581 percent
D) 2.738 percent
E) 5.000 percent