Deck 12: Differing Site Conditions

ملء الشاشة (f)
exit full mode
سؤال
Acting conscionably means to act prudently in good faith
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
In order to avoid responsibility, the Owner may rely upon

A) exculpatory clauses relieving him/her of responsibility
B) failure of the Contractor to give timely notice
C) the difference is insignificant in regard to method or approach
D) all of these
سؤال
With a Differing Site Condition, the Contract Administrator should

A) fully document all aspects of the different condition
B) meet as quickly as possible to brainstorm solutions
C) notify all parties immediately
D) all of these
سؤال
With a Differing Site Condition

A) the Contract Administrator needs to understand all the facts before alerting the Owner
B) cost will probably be more an issue than the schedule
C) timely notice by the Contractor to the Owner is important
D) the Architect will be to blame so dealing directly with the Owner is essential
سؤال
Type II Differing Site Conditions

A) differ from what is shown on the drawings
B) differ from what a prudent Contractor would expect on the site
C) are typical on most projects
D) always cause a delay
سؤال
Type I Differing Site Conditions

A) differ from what is shown on the drawings
B) differ from what a prudent Contractor would expect on the site
C) are typical on most projects
D) always cause a delay
سؤال
Reliance upon the Spearin Doctrine is sufficient for relief from Differing Site Conditions
سؤال
Type I Differing Site Conditions should have been anticipated
سؤال
Differing Site Conditions usually refers to something unexpected underground, but it does not have to be so
سؤال
A Type II Differing Site Condition is what no one would have expected to exist without regard to what was indicated on the drawings
سؤال
A Type I Differing Site Condition is when actual conditions are not what was indicated on the drawings
سؤال
A force majeure is caused by natural events but not by humans
سؤال
Through an exculpatory clause, an Owner will place responsibility on the Contractor for actions caused by the Owner's agents
سؤال
If there is an exculpatory clause protecting the Owner, key for the Contractor in resolving a Differing Site Condition favorably will be

A) how much the Differing Site Condition will cost
B) the reasonableness of the Owner
C) on whose side the Architect is
D) exculpatory clauses that favor the Contractor
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/14
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 12: Differing Site Conditions
1
Acting conscionably means to act prudently in good faith
True
2
In order to avoid responsibility, the Owner may rely upon

A) exculpatory clauses relieving him/her of responsibility
B) failure of the Contractor to give timely notice
C) the difference is insignificant in regard to method or approach
D) all of these
D
3
With a Differing Site Condition, the Contract Administrator should

A) fully document all aspects of the different condition
B) meet as quickly as possible to brainstorm solutions
C) notify all parties immediately
D) all of these
D
4
With a Differing Site Condition

A) the Contract Administrator needs to understand all the facts before alerting the Owner
B) cost will probably be more an issue than the schedule
C) timely notice by the Contractor to the Owner is important
D) the Architect will be to blame so dealing directly with the Owner is essential
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
5
Type II Differing Site Conditions

A) differ from what is shown on the drawings
B) differ from what a prudent Contractor would expect on the site
C) are typical on most projects
D) always cause a delay
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
6
Type I Differing Site Conditions

A) differ from what is shown on the drawings
B) differ from what a prudent Contractor would expect on the site
C) are typical on most projects
D) always cause a delay
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
7
Reliance upon the Spearin Doctrine is sufficient for relief from Differing Site Conditions
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
8
Type I Differing Site Conditions should have been anticipated
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
9
Differing Site Conditions usually refers to something unexpected underground, but it does not have to be so
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
10
A Type II Differing Site Condition is what no one would have expected to exist without regard to what was indicated on the drawings
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
11
A Type I Differing Site Condition is when actual conditions are not what was indicated on the drawings
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
12
A force majeure is caused by natural events but not by humans
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
13
Through an exculpatory clause, an Owner will place responsibility on the Contractor for actions caused by the Owner's agents
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
14
If there is an exculpatory clause protecting the Owner, key for the Contractor in resolving a Differing Site Condition favorably will be

A) how much the Differing Site Condition will cost
B) the reasonableness of the Owner
C) on whose side the Architect is
D) exculpatory clauses that favor the Contractor
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 14 في هذه المجموعة.