Deck 1: Introduction

ملء الشاشة (f)
exit full mode
سؤال
The first stage in the process of preparing a detailed  estimate is quantity takeoff.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
A ____ estimate has to be prepared from a minimum amount of information because it is required at a time when the project is often little more than a vague idea in the mind of the owner.

A)preliminary
B)conceptual
C)design
D)bidding
سؤال
Once the design of a project is under way, budget amounts can be established for the various elements of the project using procedures for a ____ estimate.

A)conceptual
B)preliminary
C)design
D)final
سؤال
A construction management organization seeks to facilitate overlap between project stages, often referred to as ____, to allow earlier completion of the project.

A)parallel phasing
B)fast tracking
C)project rollout
D)simultaneous staging
سؤال
The different project delivery systems use the same types of estimates- conceptual, preliminary and detailed-at various stages in the development of the project.
سؤال
There are four principal stages in the process of detailed estimating.
سؤال
In the process of __________, the estimated cost of each element in the cost plan is compared with the perceived value of that element to consider if the sum allocated to that component part of the building is justified.

A)budget analysis
B)budget accounting
C)value analysis
D)value accounting
سؤال
Most general contractors and subtrades enter into cost-plus contracts in order to perform a defined scope of work.
سؤال
____ contracts are usually the owner's choice of last resort because they can place the owner in a vulnerable financial position.

A)Cost-plus
B)Unit-price
C)Contingency
D)Fixed cost
سؤال
As costs and benefits are usually extended over a number of years, monetary value of a project will normally be determined by means of "future worth" analysis or other "time value of money" concepts.
سؤال
Cost budgets are compiled in a ____, which is a summary of all anticipated project expenditures.

A)cost plan
B)cost analysis
C)cost estimate
D)value analysis
سؤال
____ contracts are based on a pricing schedule that consists of a breakdown of the work and estimated quantities for each of the items on the breakdown.

A)Cost-based
B)Schedule-based
C)Item-price
D)Unit-price
سؤال
With the design-build method, the owner indicates that he or she requires a certain facility and usually outlines some parameters relating to location, size, design, and the desired time of occupancy.
سؤال
In the schematic phase of the construction process, the owner considers the feasibility of the proposed project.
سؤال
The Occupational Safety and Health Administration (OSHA)safety standards are the law, and contractors who fail to comply with the requirements of this legislation face possible fines or even imprisonment.
سؤال
The basis of a ____ is the accurate assessment of the work in the form of a quantity takeoff that can only be obtained from the full design of the project.

A)fixed estimate
B)detailed estimate
C)quantitative estimate
D)design estimate
سؤال
We put together estimates all the time in our everyday lives, often with little or no calculating.
سؤال
Which of the following stages in the process of detailed estimating pertains to the work to be performed by the contractor as measured in accordance with standard rules of measurement?

A)Recap quantities
B)Pricing the recap
C)Quantity takeoff
D)Recap quantities
سؤال
The cost-plus contract method is far more likely to produce a price that is an accurate forecast of the actual costs of building a construction project than any other estimating method.
سؤال
A(n)____ in its essence is an assessment of the probable total cost of some future activity.

A)proposal
B)bid
C)estimate
D)specification
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/20
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 1: Introduction
1
The first stage in the process of preparing a detailed  estimate is quantity takeoff.
True
2
A ____ estimate has to be prepared from a minimum amount of information because it is required at a time when the project is often little more than a vague idea in the mind of the owner.

A)preliminary
B)conceptual
C)design
D)bidding
B
3
Once the design of a project is under way, budget amounts can be established for the various elements of the project using procedures for a ____ estimate.

A)conceptual
B)preliminary
C)design
D)final
B
4
A construction management organization seeks to facilitate overlap between project stages, often referred to as ____, to allow earlier completion of the project.

A)parallel phasing
B)fast tracking
C)project rollout
D)simultaneous staging
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
5
The different project delivery systems use the same types of estimates- conceptual, preliminary and detailed-at various stages in the development of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
6
There are four principal stages in the process of detailed estimating.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
7
In the process of __________, the estimated cost of each element in the cost plan is compared with the perceived value of that element to consider if the sum allocated to that component part of the building is justified.

A)budget analysis
B)budget accounting
C)value analysis
D)value accounting
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
8
Most general contractors and subtrades enter into cost-plus contracts in order to perform a defined scope of work.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
9
____ contracts are usually the owner's choice of last resort because they can place the owner in a vulnerable financial position.

A)Cost-plus
B)Unit-price
C)Contingency
D)Fixed cost
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
10
As costs and benefits are usually extended over a number of years, monetary value of a project will normally be determined by means of "future worth" analysis or other "time value of money" concepts.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
11
Cost budgets are compiled in a ____, which is a summary of all anticipated project expenditures.

A)cost plan
B)cost analysis
C)cost estimate
D)value analysis
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
12
____ contracts are based on a pricing schedule that consists of a breakdown of the work and estimated quantities for each of the items on the breakdown.

A)Cost-based
B)Schedule-based
C)Item-price
D)Unit-price
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
13
With the design-build method, the owner indicates that he or she requires a certain facility and usually outlines some parameters relating to location, size, design, and the desired time of occupancy.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
14
In the schematic phase of the construction process, the owner considers the feasibility of the proposed project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
15
The Occupational Safety and Health Administration (OSHA)safety standards are the law, and contractors who fail to comply with the requirements of this legislation face possible fines or even imprisonment.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
16
The basis of a ____ is the accurate assessment of the work in the form of a quantity takeoff that can only be obtained from the full design of the project.

A)fixed estimate
B)detailed estimate
C)quantitative estimate
D)design estimate
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
17
We put together estimates all the time in our everyday lives, often with little or no calculating.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
18
Which of the following stages in the process of detailed estimating pertains to the work to be performed by the contractor as measured in accordance with standard rules of measurement?

A)Recap quantities
B)Pricing the recap
C)Quantity takeoff
D)Recap quantities
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
19
The cost-plus contract method is far more likely to produce a price that is an accurate forecast of the actual costs of building a construction project than any other estimating method.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
20
A(n)____ in its essence is an assessment of the probable total cost of some future activity.

A)proposal
B)bid
C)estimate
D)specification
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 20 في هذه المجموعة.