Deck 5: Project Scheduling Models

ملء الشاشة (f)
exit full mode
سؤال
The critical path:

A)is the shortest path through the network.
B)is necessarily unique.
C)Is defined by activities with zero slack.
D)Shows, by elimination, which activities management can safely ignore.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Since PERT allows randomness, it is not necessary to know the precise activity precedence relations to use PERT.
سؤال
Resource leveling can apply to either costs or to the time of people working on the project.
سؤال
If a critical task is delayed, we either must add resources, miss the project deadline, or sacrifice quality.
سؤال
The "forward pass" determines the earliest start and finish times for activities in a project.The "backward pass" establishes latest start and finish times.
سؤال
The earliest start (ES) time for an activity is the latest earliest finish (EF) time of all its immediate predecessors.
سؤال
Any attempt at resource leveling always will involve lengthening the project completion time beyond its "non-leveled" minimum.
سؤال
A Gantt chart, by definition, does not show precedence relations.However, you could add precedence relations by drawing arrows on the Gantt chart.
سؤال
The critical path shows the earliest project completion date by finding the shortest path through the directed network.
سؤال
The earliest start time (ES) of an activity:

A)equals its earliest finish time (EF) minus task time.
B)equals the minimum earliest finish time (EF) of all immediate predecessors.
C)equals the latest start time (LS) for non-critical activities.
D)may not be the same for two or more activities.
سؤال
A PERT/CPM network can be represented as a linear programming model by letting the decision variables be the activity start times.
سؤال
In project scheduling, activities:

A)must be completed sequentially.
B)are the tasks of a project.
C)are work packages.
D)are not represented on Gantt charts.
سؤال
Typically, the first step in project scheduling is the construction of a:

A)Gantt chart.
B)Critical path chart.
C)PERT chart.
D)set of precedence relationships between the activities.
سؤال
In PERT, the acceptance of a Beta distribution for activity completion times and the presence of a sufficient number of activities, lead to the assumption of a normal distribution of possible completion times for the overall project.
سؤال
PERT (Program Evaluation and Review Technique) generally treats activity completion times as probabilistic and:

A)is used to construct a Gantt chart.
B)is used to determine the probability that a project will be complete within a given time frame.
C)can be used to determine the exact completion time of an activity.
D)can be used to determine the exact completion time of a project.
سؤال
GANTT stands for "Generalized Activity Normalization Time Table."
سؤال
The critical path is always unique.
سؤال
Overall project completion time will not be affected if an activity possessing slack time is started at any time between its earliest and latest start time.
سؤال
Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500.Under maximum crashing, activity D can be completed is 4 weeks for $2,300.Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.
سؤال
A disadvantage of Gantt chart methodology is that an earliest possible completion date for the project cannot be determined.
سؤال
When attempting to use PERT methodology, how do you estimate the mean completion time and standard deviation when, for a given activity, the time estimates a, b, and m (pessimistic, optimistic, and most likely) are all identical? What implications does this have if several activities have this property?
سؤال
In the critical path method (CPM), crashing does not:

A)deal with accelerating a project's overall completion time.
B)assume that every activity completion time can be crashed.
C)require two time estimates for each activity's duration time.
D)take into account the possibility of creating multiple critical paths.
سؤال
Activity T has a single immediate predecessor, activity S.However, T may actually be initiated anytime after S is 50% complete.Can this situation be accommodated using standard project scheduling techniques? Explain.
سؤال
Let Ti = normal completion time for task iRi = crash completion time for task i Ci = normal cost for task i
Hi = crash cost for task i
Xi = start time for task i
Yi = amount of time by which task i is to be crashed.
What is the objective function of a linear programming model for project crashing?

A) Σ\Sigma all i Yi(Hi - Ci)/(Ti - Ri)
B) Σ\Sigma all i on critical path Yi(Hi - Ci)/(Ti - Ri)
C) Σ\Sigma all i XiYi
D) Σ\Sigma all i YiHi
سؤال
A "forward pass" in network analysis of a project, determines:

A)earliest times.
B)latest times.
C)slack times.
D)most likely times.
سؤال
Which of the following is true?

A)PERT gives a better solution than the expected value criterion.
B)To use the expected value criterion, we must know every possible outcome.
C)The expected value criterion determines the optimal decision by choosing the best expected payoff.
D)Adding resources will decrease the project time to completion.
سؤال
The probabilistic approach characterized by PERT does not use:

A)optimistic activity times.
B)median activity times.
C)pessimistic activity times.
D)most likely activity times.
سؤال
Discuss the assumptions required for determining the probability that a project will be completed within a certain time period by using a normal distribution of the activity time along the critical path determined by mean completion times of the critical activities.Do you think they are realistic for most projects?
سؤال
In the PERT probabilistic approach, statisticians have found which distribution most helpful in describing possible activity times?

A)Beta
B)Gamma
C)normal
D)uniform
سؤال
Activity C is an immediate predecessor of activity G.Both activities have 4 hours of slack time.If both activities are delayed 3 hours, and these are the only delays, the overall effect of these delays is to delay the minimum project completion time by:

A)0 hours.
B)2 hours.
C)6 hours.
D)The overall delay cannot be determined with only this information.
سؤال
Ajax is about to embark on a project involving the design, manufacture, and introduction of a new microwave oven.The first three activities and the immediate predecessors are:  Activity  Predecessor  A  Prototype Design  none  B  Acquisition of Materials  A  C  Prototype Construction  B \begin{array}{lcc}&\text { Activity } &\text { Predecessor }\\\text { A } & \text { Prototype Design } & \text { none } \\\text { B } & \text { Acquisition of Materials } & \text { A } \\\text { C } & \text { Prototype Construction } & \text { B }\end{array}
However, it has not yet been decided whether the prototype materials will be purchased from a vendor (taking two weeks) or produced in another Ajax division (four weeks).What are the implications of this regarding usage of any standard project scheduling technique?
سؤال
A project contains activities D and K.Activity D has 5 hours of slack, and activity K has 7 hours of slack.If activity D is delayed 4 hours, activity K is delayed 6 hours, and these are the only delays, then the overall effect of these delays is to delay the minimum project completion time by:

A)0 hours.
B)2 hours.
C)11 hours.
D)The overall delay cannot be determined with only this information.
سؤال
Which of the following is not a fundamental, inherent weakness in the probabilistic approach to PERT?

A)One may have difficulty in obtaining three reliable time estimates for each activity.
B)There is the possibility of large variances for non-critical activities.
C)The assumption that activity times are independent of each other.
D)The assumption that possible overall project completion times are Beta-distributed.
سؤال
PERT/Cost is a cost-center based system, where the "centers" are:

A)locations.
B)work packages of groups of related activities.
C)activities.
D)departments.
سؤال
PERT/Cost:

A)allows for activity interruption.
B)assumes costs are evenly spread over time.
C)monitors project performance relation to cost, not time.
D)cannot help identify cost under-runs.
سؤال
Let B = budgeted total cost for a work package T = estimated completion time for a work package
P = percent complete
A = actual expenses to date
M = time used to date
What is the definition of cost overrun, C?

A)C = A - PB
B)C = A - (1 - P)TB
C)C = A - PTB
D)C = A - MB/T
سؤال
Which of the following is false?

A)Crashing an activity on the critical path can cause another path to become the critical path.
B)The maximum crash time reduction for each and every activity is limited.
C)CPM assumes that adding resources to crash an activity from its normal time to its crash time will reach a point of diminishing returns.
D)Crashing non-critical activities will not reduce the project time.
سؤال
In using PERT/CPM, why does management need to pay any attention at all to non-critical path activities?
سؤال
Which statement does not represent a set of constraints for a linear programming approach to project crashing?

A)There is a limit to the time reduction for each activity.
B)No activity can be reduced more than its slack time.
C)Activity start time must be greater than the finish time of all immediate predecessors.
D)The project must be completed by the deadline (or within budget).
سؤال
Which of the following is true?

A)Slack = (LF - LS)
B)(LF - LS) > (EF - ES)
C)Slack is never "shared."
D)(LS - ES) \ge 0
سؤال
Given the following data for work packages in a PERT/Cost network at week 18:
 Activity  Immediate  Predecessors  Budgeted  Time  (weeks)  Budgeted  Value  Percent  Complete  Expense To  Date  A 12$50,0001008$48,000 B 8$20,0001008$21,000 C  A 6$60,000758$40,000 D  B 16$40,000508$25,000 E  C, D 16$45,000080 F  B 28$80,000758$55,000\begin{array}{cccccc}\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessors }\end{array} & \begin{array}{c}\text { Budgeted } \\\text { Time } \\\text { (weeks) }\end{array} & \begin{array}{c}\text { Budgeted } \\\text { Value }\end{array} & \begin{array}{c}\text { Percent } \\\text { Complete }\end{array} & \begin{array}{c}\text { Expense To } \\\text { Date }\end{array} \\\text { A } & -- & 12 & \$ 50,000 & 1008 & \$ 48,000 \\\text { B } & -- & 8 & \$ 20,000 & 1008 & \$ 21,000 \\\text { C } & \text { A } & 6 & \$ 60,000 & 758 & \$ 40,000 \\\text { D } & \text { B } & 16 & \$ 40,000 & 508 & \$ 25,000 \\\text { E } & \text { C, D } & 16 & \$ 45,000 & 08 & 0 \\\text { F } & \text { B } & 28 & \$ 80,000 & 758 & \$ 55,000\end{array}
A.Is the project currently experiencing a cost overrun?
B.Is the project on target to be completed within 40 weeks?
C.What corrective action, if any, could you recommend?
سؤال
Explain the Excel functions
NORMINV(0.98,200,10)
NORMDIST(190,200,10,TRUE).
سؤال
Why must we solve two linear programming models to model a PERT/CPM network?
سؤال
A project consists of the following seven activities and immediate predecessors:  Artivity  Predecegsor  A  None  B  A  C  A  D  B  E  B, C  F  D, E  G  F \begin{array} { c c } \text { Artivity } & \text { Predecegsor } \\\text { A } & \text { None } \\\text { B } & \text { A } \\\text { C } & \text { A } \\ \text { D } & \text { B } \\\text { E } & \text { B, C }\\\text { F } & \text { D, E }\\\text { G } & \text { F }\end{array} Construct an AON network diagram for the project.
سؤال
Activity A is critical.Activity B has a slack time of 5 days.What is the impact of a 7 day delay in either A or B?
سؤال
For an activity, an engineer estimatesa (optimistic time) = 4
b (pessimistic time) = 11
m (most likely time) = 6
What is the mean for this activity? The variance?
سؤال
Suppose the estimated completion times for activities A through G in problem 1 were 5, 4, 3, 6, 2, 5, 2 respectively.Draw an earliest completion Gantt chart for the data.
سؤال
In a PERT network, you are given the following data with times in weeks.  Activity  Immediate  Optimistic  Most Likely  Pessimistic  Predecessors  Time  Time  Time  A  G 1113 B 4920 C  A 21114 D  A, B 5613 E  D 3611 F  C, D 91011 G  E , F 72021\begin{array}{ccccc}\text { Activity } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\& \text { Predecessors } & \text { Time } & \text { Time } & \text { Time }\\\text { A } & -- & \text { G } & 11 & 13 \\\text { B } & -- & 4 & 9 & 20 \\\text { C } & \text { A } & 2 & 11 & 14 \\\text { D } & \text { A, B } & 5 & 6 & 13 \\\text { E } & \text { D } & 3 & 6 & 11 \\\text { F } & \text { C, D } & 9 & 10 & 11 \\\text { G } & \text { E }, \text { F } & 7 & 20 & 21\end{array}
A.What is the critical path?
B.What is the probability the project will be completed within one year (52 weeks)?

C.Which activity has the most slack?
سؤال
Consider the following information for the activities comprising a small construction project which is scheduled to complete in 26 days.(Costs are in $1000's.)
 Normal  Schedule Crash Schedule  Activity  Slack  Time  Cost  Time  Cost  M 0710419 II 25656 O 047212 P 059313 Q 22516 R 04949 S 0612515\begin{array}{cccccc}&&\text { Normal }&\text { Schedule}&\text { Crash}&\text { Schedule }\\\text { Activity } & \text { Slack } & \text { Time } & \text { Cost } & \text { Time } & \text { Cost } \\\text { M } & 0 & 7 & 10 & 4 & 19 \\\text { II } & 2 & 5 & 6 & 5 & 6 \\\text { O } & 0 & 4 & 7 & 2 & 12 \\\text { P } & 0 & 5 & 9 & 3 & 13 \\\text { Q } & 2 & 2 & 5 & 1 & 6 \\\text { R } & 0 & 4 & 9 & 4 & 9 \\\text { S } & 0 & 6 & 12 & 5 & 15\end{array} A.If the project must be completed in 25 days, which activity should be accelerated? Why?
B.Will the critical path be altered?
C.What is the total estimated cost of the project on the accelerated 25 day schedule?
سؤال
For the data in problem 6,A.Using the normal times, prepare a chart giving the earliest and latest start and finish times and slack for each activity.
B.What is the critical path and the project completion time using normal times?
C.What is the effect of a 2 week delay to activity B? What is the effect of a 2 week delay to activity B combined with a 2 week delay to activity D?
سؤال
Using PERT, we have determined the mean completion time for each activity ( μ\mu j) and the standard deviation for each activity completion time ( σ\sigma j).How do we use these data to determine the overall project completion time?
سؤال
For a CPM model, you are given the following data with time in weeks.  Activity  Immediate  Predecessors  Normal  Time  Normal Cost  Crash  Time  Crash Cost  A 9320056000 B 7140052400 C  A 6150052000 D  B 5250034000 E  A, B 4180032800 F  D, E 3180014800\begin{array}{cccccc}\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessors }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time }\end{array} & \text { Normal Cost } & \begin{array}{c}\text { Crash } \\\text { Time }\end{array} & \text { Crash Cost } \\\text { A } & -- & 9 & 3200 & 5 & 6000 \\\text { B } & -- & 7 & 1400 & 5 & 2400 \\\text { C } & \text { A } & 6 & 1500 & 5 & 2000 \\\text { D } & \text { B } & 5 & 2500 & 3 & 4000 \\\text { E } & \text { A, B } & 4 & 1800 & 3 & 2800 \\\text { F } & \text { D, E } & 3 & 1800 & 1 & 4800\end{array}
A.If activity A needed to be completed in 6 weeks, what would its cost be?
B.If $3000 were allocated to activity D, how long would it take to complete?
سؤال
Consider the following activity schedule chart for a maintenance project.  Activity  ES  EF  IS  LF  A 0617 B 0505 C 614715 D 6101418 E 14161517 F 514514 G 14171417 H 14191621 I 10131821 J 17211721\begin{array}{ccccr}\text { Activity } & \text { ES } & \text { EF } & \text { IS } & \text { LF } \\\text { A } & 0 & 6 & 1 & 7 \\\text { B } & 0 & 5 & 0 & 5 \\\text { C } & 6 & 14 & 7 & 15 \\\text { D } & 6 & 10 & 14 & 18 \\\text { E } & 14 & 16 & 15 & 17 \\\text { F } & 5 & 14 & 5 & 14 \\\text { G } & 14 & 17 & 14 & 17 \\\text { H } & 14 & 19 & 16 & 21 \\\text { I } & 10 & 13 & 18 & 21 \\\text { J } & 17 & 21 & 17 & 21\end{array} A.What are the slack values?
B.Identify the activities on the critical path.
C.If the time is in weeks, what is the impact of a two week delay in activity D, H, or C?
سؤال
For the data in problem 6,
A.Write a linear programming model that will give the minimum cost solution for completing the project in 14 weeks.
B.How would your model change if the objective were to complete the project in minimum time given a budget of $15,000?
سؤال
What type of distribution does PERT assume for the activity completion times?
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/55
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 5: Project Scheduling Models
1
The critical path:

A)is the shortest path through the network.
B)is necessarily unique.
C)Is defined by activities with zero slack.
D)Shows, by elimination, which activities management can safely ignore.
C
2
Since PERT allows randomness, it is not necessary to know the precise activity precedence relations to use PERT.
False
3
Resource leveling can apply to either costs or to the time of people working on the project.
True
4
If a critical task is delayed, we either must add resources, miss the project deadline, or sacrifice quality.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
5
The "forward pass" determines the earliest start and finish times for activities in a project.The "backward pass" establishes latest start and finish times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
6
The earliest start (ES) time for an activity is the latest earliest finish (EF) time of all its immediate predecessors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
7
Any attempt at resource leveling always will involve lengthening the project completion time beyond its "non-leveled" minimum.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
8
A Gantt chart, by definition, does not show precedence relations.However, you could add precedence relations by drawing arrows on the Gantt chart.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
9
The critical path shows the earliest project completion date by finding the shortest path through the directed network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
10
The earliest start time (ES) of an activity:

A)equals its earliest finish time (EF) minus task time.
B)equals the minimum earliest finish time (EF) of all immediate predecessors.
C)equals the latest start time (LS) for non-critical activities.
D)may not be the same for two or more activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
11
A PERT/CPM network can be represented as a linear programming model by letting the decision variables be the activity start times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
12
In project scheduling, activities:

A)must be completed sequentially.
B)are the tasks of a project.
C)are work packages.
D)are not represented on Gantt charts.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
13
Typically, the first step in project scheduling is the construction of a:

A)Gantt chart.
B)Critical path chart.
C)PERT chart.
D)set of precedence relationships between the activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
14
In PERT, the acceptance of a Beta distribution for activity completion times and the presence of a sufficient number of activities, lead to the assumption of a normal distribution of possible completion times for the overall project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
15
PERT (Program Evaluation and Review Technique) generally treats activity completion times as probabilistic and:

A)is used to construct a Gantt chart.
B)is used to determine the probability that a project will be complete within a given time frame.
C)can be used to determine the exact completion time of an activity.
D)can be used to determine the exact completion time of a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
16
GANTT stands for "Generalized Activity Normalization Time Table."
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
17
The critical path is always unique.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
18
Overall project completion time will not be affected if an activity possessing slack time is started at any time between its earliest and latest start time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
19
Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500.Under maximum crashing, activity D can be completed is 4 weeks for $2,300.Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
20
A disadvantage of Gantt chart methodology is that an earliest possible completion date for the project cannot be determined.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
21
When attempting to use PERT methodology, how do you estimate the mean completion time and standard deviation when, for a given activity, the time estimates a, b, and m (pessimistic, optimistic, and most likely) are all identical? What implications does this have if several activities have this property?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
22
In the critical path method (CPM), crashing does not:

A)deal with accelerating a project's overall completion time.
B)assume that every activity completion time can be crashed.
C)require two time estimates for each activity's duration time.
D)take into account the possibility of creating multiple critical paths.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
23
Activity T has a single immediate predecessor, activity S.However, T may actually be initiated anytime after S is 50% complete.Can this situation be accommodated using standard project scheduling techniques? Explain.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
24
Let Ti = normal completion time for task iRi = crash completion time for task i Ci = normal cost for task i
Hi = crash cost for task i
Xi = start time for task i
Yi = amount of time by which task i is to be crashed.
What is the objective function of a linear programming model for project crashing?

A) Σ\Sigma all i Yi(Hi - Ci)/(Ti - Ri)
B) Σ\Sigma all i on critical path Yi(Hi - Ci)/(Ti - Ri)
C) Σ\Sigma all i XiYi
D) Σ\Sigma all i YiHi
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
25
A "forward pass" in network analysis of a project, determines:

A)earliest times.
B)latest times.
C)slack times.
D)most likely times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
26
Which of the following is true?

A)PERT gives a better solution than the expected value criterion.
B)To use the expected value criterion, we must know every possible outcome.
C)The expected value criterion determines the optimal decision by choosing the best expected payoff.
D)Adding resources will decrease the project time to completion.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
27
The probabilistic approach characterized by PERT does not use:

A)optimistic activity times.
B)median activity times.
C)pessimistic activity times.
D)most likely activity times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
28
Discuss the assumptions required for determining the probability that a project will be completed within a certain time period by using a normal distribution of the activity time along the critical path determined by mean completion times of the critical activities.Do you think they are realistic for most projects?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
29
In the PERT probabilistic approach, statisticians have found which distribution most helpful in describing possible activity times?

A)Beta
B)Gamma
C)normal
D)uniform
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
30
Activity C is an immediate predecessor of activity G.Both activities have 4 hours of slack time.If both activities are delayed 3 hours, and these are the only delays, the overall effect of these delays is to delay the minimum project completion time by:

A)0 hours.
B)2 hours.
C)6 hours.
D)The overall delay cannot be determined with only this information.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
31
Ajax is about to embark on a project involving the design, manufacture, and introduction of a new microwave oven.The first three activities and the immediate predecessors are:  Activity  Predecessor  A  Prototype Design  none  B  Acquisition of Materials  A  C  Prototype Construction  B \begin{array}{lcc}&\text { Activity } &\text { Predecessor }\\\text { A } & \text { Prototype Design } & \text { none } \\\text { B } & \text { Acquisition of Materials } & \text { A } \\\text { C } & \text { Prototype Construction } & \text { B }\end{array}
However, it has not yet been decided whether the prototype materials will be purchased from a vendor (taking two weeks) or produced in another Ajax division (four weeks).What are the implications of this regarding usage of any standard project scheduling technique?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
32
A project contains activities D and K.Activity D has 5 hours of slack, and activity K has 7 hours of slack.If activity D is delayed 4 hours, activity K is delayed 6 hours, and these are the only delays, then the overall effect of these delays is to delay the minimum project completion time by:

A)0 hours.
B)2 hours.
C)11 hours.
D)The overall delay cannot be determined with only this information.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
33
Which of the following is not a fundamental, inherent weakness in the probabilistic approach to PERT?

A)One may have difficulty in obtaining three reliable time estimates for each activity.
B)There is the possibility of large variances for non-critical activities.
C)The assumption that activity times are independent of each other.
D)The assumption that possible overall project completion times are Beta-distributed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
34
PERT/Cost is a cost-center based system, where the "centers" are:

A)locations.
B)work packages of groups of related activities.
C)activities.
D)departments.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
35
PERT/Cost:

A)allows for activity interruption.
B)assumes costs are evenly spread over time.
C)monitors project performance relation to cost, not time.
D)cannot help identify cost under-runs.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
36
Let B = budgeted total cost for a work package T = estimated completion time for a work package
P = percent complete
A = actual expenses to date
M = time used to date
What is the definition of cost overrun, C?

A)C = A - PB
B)C = A - (1 - P)TB
C)C = A - PTB
D)C = A - MB/T
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
37
Which of the following is false?

A)Crashing an activity on the critical path can cause another path to become the critical path.
B)The maximum crash time reduction for each and every activity is limited.
C)CPM assumes that adding resources to crash an activity from its normal time to its crash time will reach a point of diminishing returns.
D)Crashing non-critical activities will not reduce the project time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
38
In using PERT/CPM, why does management need to pay any attention at all to non-critical path activities?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
39
Which statement does not represent a set of constraints for a linear programming approach to project crashing?

A)There is a limit to the time reduction for each activity.
B)No activity can be reduced more than its slack time.
C)Activity start time must be greater than the finish time of all immediate predecessors.
D)The project must be completed by the deadline (or within budget).
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
40
Which of the following is true?

A)Slack = (LF - LS)
B)(LF - LS) > (EF - ES)
C)Slack is never "shared."
D)(LS - ES) \ge 0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
41
Given the following data for work packages in a PERT/Cost network at week 18:
 Activity  Immediate  Predecessors  Budgeted  Time  (weeks)  Budgeted  Value  Percent  Complete  Expense To  Date  A 12$50,0001008$48,000 B 8$20,0001008$21,000 C  A 6$60,000758$40,000 D  B 16$40,000508$25,000 E  C, D 16$45,000080 F  B 28$80,000758$55,000\begin{array}{cccccc}\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessors }\end{array} & \begin{array}{c}\text { Budgeted } \\\text { Time } \\\text { (weeks) }\end{array} & \begin{array}{c}\text { Budgeted } \\\text { Value }\end{array} & \begin{array}{c}\text { Percent } \\\text { Complete }\end{array} & \begin{array}{c}\text { Expense To } \\\text { Date }\end{array} \\\text { A } & -- & 12 & \$ 50,000 & 1008 & \$ 48,000 \\\text { B } & -- & 8 & \$ 20,000 & 1008 & \$ 21,000 \\\text { C } & \text { A } & 6 & \$ 60,000 & 758 & \$ 40,000 \\\text { D } & \text { B } & 16 & \$ 40,000 & 508 & \$ 25,000 \\\text { E } & \text { C, D } & 16 & \$ 45,000 & 08 & 0 \\\text { F } & \text { B } & 28 & \$ 80,000 & 758 & \$ 55,000\end{array}
A.Is the project currently experiencing a cost overrun?
B.Is the project on target to be completed within 40 weeks?
C.What corrective action, if any, could you recommend?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
42
Explain the Excel functions
NORMINV(0.98,200,10)
NORMDIST(190,200,10,TRUE).
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
43
Why must we solve two linear programming models to model a PERT/CPM network?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
44
A project consists of the following seven activities and immediate predecessors:  Artivity  Predecegsor  A  None  B  A  C  A  D  B  E  B, C  F  D, E  G  F \begin{array} { c c } \text { Artivity } & \text { Predecegsor } \\\text { A } & \text { None } \\\text { B } & \text { A } \\\text { C } & \text { A } \\ \text { D } & \text { B } \\\text { E } & \text { B, C }\\\text { F } & \text { D, E }\\\text { G } & \text { F }\end{array} Construct an AON network diagram for the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
45
Activity A is critical.Activity B has a slack time of 5 days.What is the impact of a 7 day delay in either A or B?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
46
For an activity, an engineer estimatesa (optimistic time) = 4
b (pessimistic time) = 11
m (most likely time) = 6
What is the mean for this activity? The variance?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
47
Suppose the estimated completion times for activities A through G in problem 1 were 5, 4, 3, 6, 2, 5, 2 respectively.Draw an earliest completion Gantt chart for the data.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
48
In a PERT network, you are given the following data with times in weeks.  Activity  Immediate  Optimistic  Most Likely  Pessimistic  Predecessors  Time  Time  Time  A  G 1113 B 4920 C  A 21114 D  A, B 5613 E  D 3611 F  C, D 91011 G  E , F 72021\begin{array}{ccccc}\text { Activity } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\& \text { Predecessors } & \text { Time } & \text { Time } & \text { Time }\\\text { A } & -- & \text { G } & 11 & 13 \\\text { B } & -- & 4 & 9 & 20 \\\text { C } & \text { A } & 2 & 11 & 14 \\\text { D } & \text { A, B } & 5 & 6 & 13 \\\text { E } & \text { D } & 3 & 6 & 11 \\\text { F } & \text { C, D } & 9 & 10 & 11 \\\text { G } & \text { E }, \text { F } & 7 & 20 & 21\end{array}
A.What is the critical path?
B.What is the probability the project will be completed within one year (52 weeks)?

C.Which activity has the most slack?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
49
Consider the following information for the activities comprising a small construction project which is scheduled to complete in 26 days.(Costs are in $1000's.)
 Normal  Schedule Crash Schedule  Activity  Slack  Time  Cost  Time  Cost  M 0710419 II 25656 O 047212 P 059313 Q 22516 R 04949 S 0612515\begin{array}{cccccc}&&\text { Normal }&\text { Schedule}&\text { Crash}&\text { Schedule }\\\text { Activity } & \text { Slack } & \text { Time } & \text { Cost } & \text { Time } & \text { Cost } \\\text { M } & 0 & 7 & 10 & 4 & 19 \\\text { II } & 2 & 5 & 6 & 5 & 6 \\\text { O } & 0 & 4 & 7 & 2 & 12 \\\text { P } & 0 & 5 & 9 & 3 & 13 \\\text { Q } & 2 & 2 & 5 & 1 & 6 \\\text { R } & 0 & 4 & 9 & 4 & 9 \\\text { S } & 0 & 6 & 12 & 5 & 15\end{array} A.If the project must be completed in 25 days, which activity should be accelerated? Why?
B.Will the critical path be altered?
C.What is the total estimated cost of the project on the accelerated 25 day schedule?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
50
For the data in problem 6,A.Using the normal times, prepare a chart giving the earliest and latest start and finish times and slack for each activity.
B.What is the critical path and the project completion time using normal times?
C.What is the effect of a 2 week delay to activity B? What is the effect of a 2 week delay to activity B combined with a 2 week delay to activity D?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
51
Using PERT, we have determined the mean completion time for each activity ( μ\mu j) and the standard deviation for each activity completion time ( σ\sigma j).How do we use these data to determine the overall project completion time?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
52
For a CPM model, you are given the following data with time in weeks.  Activity  Immediate  Predecessors  Normal  Time  Normal Cost  Crash  Time  Crash Cost  A 9320056000 B 7140052400 C  A 6150052000 D  B 5250034000 E  A, B 4180032800 F  D, E 3180014800\begin{array}{cccccc}\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessors }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time }\end{array} & \text { Normal Cost } & \begin{array}{c}\text { Crash } \\\text { Time }\end{array} & \text { Crash Cost } \\\text { A } & -- & 9 & 3200 & 5 & 6000 \\\text { B } & -- & 7 & 1400 & 5 & 2400 \\\text { C } & \text { A } & 6 & 1500 & 5 & 2000 \\\text { D } & \text { B } & 5 & 2500 & 3 & 4000 \\\text { E } & \text { A, B } & 4 & 1800 & 3 & 2800 \\\text { F } & \text { D, E } & 3 & 1800 & 1 & 4800\end{array}
A.If activity A needed to be completed in 6 weeks, what would its cost be?
B.If $3000 were allocated to activity D, how long would it take to complete?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
53
Consider the following activity schedule chart for a maintenance project.  Activity  ES  EF  IS  LF  A 0617 B 0505 C 614715 D 6101418 E 14161517 F 514514 G 14171417 H 14191621 I 10131821 J 17211721\begin{array}{ccccr}\text { Activity } & \text { ES } & \text { EF } & \text { IS } & \text { LF } \\\text { A } & 0 & 6 & 1 & 7 \\\text { B } & 0 & 5 & 0 & 5 \\\text { C } & 6 & 14 & 7 & 15 \\\text { D } & 6 & 10 & 14 & 18 \\\text { E } & 14 & 16 & 15 & 17 \\\text { F } & 5 & 14 & 5 & 14 \\\text { G } & 14 & 17 & 14 & 17 \\\text { H } & 14 & 19 & 16 & 21 \\\text { I } & 10 & 13 & 18 & 21 \\\text { J } & 17 & 21 & 17 & 21\end{array} A.What are the slack values?
B.Identify the activities on the critical path.
C.If the time is in weeks, what is the impact of a two week delay in activity D, H, or C?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
54
For the data in problem 6,
A.Write a linear programming model that will give the minimum cost solution for completing the project in 14 weeks.
B.How would your model change if the objective were to complete the project in minimum time given a budget of $15,000?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
55
What type of distribution does PERT assume for the activity completion times?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 55 في هذه المجموعة.