Deck 10: Integer Programming, Goal Programming, and Nonlinear Programming

ملء الشاشة (f)
exit full mode
سؤال
An integer programming solution can never produce a greater profit objective than the LP solution to the same problem.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
A 0-1 programming representation could be used to assign sections of a course to specific classrooms.
سؤال
The following objective function is nonlinear: Max 5X - 8YZ.
سؤال
In goal programming, the deviational variables have the same objective function coefficients as the surplus and slack variables in a normal linear program.
سؤال
Nonlinear programming is the case in which objectives and/or constraints are nonlinear.
سؤال
Unfortunately, multiple goals in goal programming are not able to be prioritized and solved.
سؤال
There is no general method for solving all nonlinear problems.
سؤال
The following objective function is nonlinear: Max 5X + (1/8)Y - Z.
سؤال
In goal programming, if all the goals are achieved, then the value of the objective function will always be zero.
سؤال
The constraint X1 + X2 ≤ 1 with 0 -1 integer programming allows for either X1 or X2 to be a part of the optimal solution, but not both.
سؤال
Quadratic programming contains squared terms in the constraints.
سؤال
The transportation problem is a good example of a pure integer programming problem.
سؤال
The three types of integer programs are: pure integer programming, impure integer programming, and 0-1 integer programming.
سؤال
Goal programming permits multiple objectives to be satisfied.
سؤال
Requiring an integer solution to a linear programming problem decreases the size of the feasible region.
سؤال
If conditions require that all decision variables must have an integer solution, then the class of problem described is an integer programming problem.
سؤال
0-1 integer programming might be applicable to selecting the best gymnastics team to represent a country from among all identified teams.
سؤال
When solving very large integer programming problems, we sometimes have to settle for a "good," not necessarily optimal, answer.
سؤال
Unfortunately, goal programming, while able to handle multiple objectives, is unable to prioritize these objectives.
سؤال
In goal programming, our goal is to drive the deviational variables in the objective function as close to zero as possible.
سؤال
The global optimum point may be superior to nearby points, but the local optimum point is the true optimal solution-n to a nonlinear programming problem.
سؤال
The constraint X1 - X2 ≤ 0 with 0 -1 integer programming allows for X1 to be selected as part of the optimal solution only if X2 is selected to be a part of the optimal solution, but not both.
سؤال
An integer programming (maximization)problem was first solved as a linear programming problem, and the objective function value (profit)was $253.67.The two decision variables (X, Y)in the problem had values of X = 12.45 and Y = 32.75.If there is a single optimal solution, which of the following must be true for the optimal integer solution to this problem?

A)X = 12 Y = 32
B)X = 12 Y = 33
C)The objective function value must be less than $253.67.
D)The objective function value will be greater than $253.67.
سؤال
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a profit of $2,400 and goal number 2 was to have no idle time for workers in the factory.The optimal solution to this problem resulted in a profit of $2,300 and no idle time.What was the value for the objective function for this goal programming problem?

A)2300
B)100
C)-100
D)0
سؤال
We do not have a general method for solving all types of ________ problems.

A)mixed-integer programming
B)0-1 integer programming
C)goal programming
D)nonlinear programming
سؤال
A capital budgeting problem involving the selection of possible projects under budget constraints is solved by which of the following?

A)mixed-integer programming
B)0-1 integer programming
C)goal programming
D)nonlinear programming
سؤال
A mathematical programming model that permits decision makers to set and prioritize multiple objective functions is called a

A)pure-integer programming problem.
B)mixed-integer programming problem.
C)zero-one integer programming problem.
D)goal programming problem.
سؤال
Goal programming differs from linear programming in which of the following aspects?

A)It tries to maximize deviations between set goals and what can be achieved within the constraints.
B)It minimizes instead of maximizing as in LP.
C)It permits multiple goals to be combined into one objective function.
D)It maximizes instead of minimizing as in LP.
سؤال
The constraint X1 - X2 = 0 with 0 -1 integer programming allows for either both X1 and X2 to be selected to be a part of the optimal solution, or for neither to be selected.
سؤال
The following objective function is nonlinear: Max 5X + X/Y - Z.
سؤال
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a profit of $3,600 and goal number 2 was to have no wasted material.The optimal solution to this problem resulted in a profit of $3,300 and no wasted material.What was the value for the objective function for this goal programming problem?

A)300
B)-300
C)3300
D)0
سؤال
Assignment problems solved previously by linear programming techniques are also examples of

A)pure-integer programming problems.
B)mixed-integer programming problems.
C)zero-one integer programming problems.
D)goal programming problems.
سؤال
The constraint X1 + X2 + X3+ X4 ≤ 2 with 0 -1 integer programming allows at most two of the items X1, X2, X3, and X4 to be selected to be a part of the optimal solution.
سؤال
Which of the following is a category of mathematical programming techniques that doesn't assume linearity in the objective function and/or constraints?

A)integer programs
B)goal programming problems
C)nonlinear programs
D)multiple objective programming problems
سؤال
In an integer programming problem, if it is desired to have variable X be exactly twice the value of variable Y, the constraint would be written

A)2X + Y = 0.
B)X + 2Y = 0.
C)2X - Y = 0.
D)X - 2Y = 0.
سؤال
A model containing a linear objective function and linear constraints but requiring that one or more of the decision variables take on an integer value in the final solution is called

A)a goal programming problem.
B)an integer programming problem.
C)a nonlinear programming problem.
D)a multiple objective LP problem.
سؤال
In a goal programming problem with two goals at the same priority level, all the deviational variables are equal to zero in the optimal solution.This means

A)there is no feasible solution to the problem.
B)all goals are fully achieved.
C)nonlinear programming must be used to solve this.
D)this problem was an integer programming problem.
سؤال
An integer programming (minimization)problem was first solved as a linear programming problem, and the objective function value (cost)was $253.67.The two decision variables (X, Y)in the problem had values of X = 12.45 and Y = 32.75.If there is a single optimal solution, which of the following must be true for the optimal integer solution to this problem?

A)X = 13 Y = 33
B)X = 12 Y = 32
C)The objective function value must be less than $253.67.
D)The objective function value will be greater than $253.67.
سؤال
Goal programming is characterized by

A)all maximization problems.
B)setting of lower and upper bounds.
C)the deviation from a high-priority goal must be minimized before the next-highest-priority goal may be considered.
D)deviation from certainty.
سؤال
Which of the following functions is nonlinear?

A)4X + 2Y + 7Z
B)-4X + 2Y
C)4X + (1/2)Y + 7Z
D)4X/Y + 7Z
سؤال
Consider the following 0-1 integer programming problem: Minimize 20X + 36Y +24Z
Subject to: 2X + 4Y + 3Z ≥ 7
12X + 8Y + 10Z ≥ 25
X, Y, Z must be 0 or 1
If we wish to add the constraint that no more than two of these variables must be positive, how would this be written?

A)2X + 2Y + 2Z ≤ 3
B)X + Y + Z ≤ 2
C)X ≤ 2, and Y ≤ 2, and Z ≤ 2
D)X, Y, Z ≤ 2
سؤال
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a cost of $3,600 and goal number 2 was to have no wasted material.The optimal solution to this problem resulted in a cost of $3,900 and no wasted material.What was the value for the objective function for this goal programming problem?

A)300
B)-300
C)3300
D)0
سؤال
The overall best solution in a nonlinear program is a

A)global optimum.
B)local optimum.
C)binary optimum.
D)nonlinear optimum.
سؤال
Which of the following is not considered nonlinear programming?

A)nonlinear objective and nonlinear constraints
B)nonlinear objective with linear constraints
C)binary decision variable with nonlinear constraints
D)integer decision variable with linear constraints
سؤال
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a cost of $3,600 and goal number 2 was to complete the task in 400 hours or fewer.The optimal solution to this problem resulted in a cost of $3,600 and a completion time of 420 hours.What was the value for the objective function for this goal programming problem?

A)400
B)-400
C)20
D)0
سؤال
Consider the following 0-1 integer programming problem: Minimize 20X + 36Y + 24Z
Subject to: 2X + 4Y + 3Z ≥ 7
12X + 8Y + 10Z ≥ 25
X, Y, Z must be 0 or 1
If we wish to add the constraint that X must be positive, and that only Y or Z, but not both, can be positive, how would the additional constraint(s)be written?

A)X + Y + Z ≤ 3, Y + Z ≤ 1
B)X ≤ 1, Y + Z = 1
C)X ≤ 2, and Y ≤ 2, and Z ≤ 2
D)X = 1, Y + Z ≤ 1
سؤال
Another name for a 0-1 variable is a(n)________ variable.

A)either-or
B)binary
C)yes-no
D)quadratic
سؤال
A transportation problem is an example of

A)a pure-integer programming problem.
B)a mixed-integer programming problem.
C)a zero-one integer programming problem.
D)a goal programming problem.
سؤال
The concept of "satisficing" is affiliated with which of the following?

A)mixed integer programming
B)integer programming
C)nonlinear programming
D)goal programming
سؤال
Agile Bikes has manufacturing plants in Salt Lake City, Dallas, and Chicago.The bikes are shipped to retail stores in Los Angeles, New York, Miami, and Seattle.Information on shipping costs, supply, and demand is given in the following table: <strong>Agile Bikes has manufacturing plants in Salt Lake City, Dallas, and Chicago.The bikes are shipped to retail stores in Los Angeles, New York, Miami, and Seattle.Information on shipping costs, supply, and demand is given in the following table:   Where should Los Angeles receive their bicycles from?</strong> A)Salt Lake City and Chicago B)Salt Lake City and Dallas C)Chicago and Dallas D)Dallas <div style=padding-top: 35px> Where should Los Angeles receive their bicycles from?

A)Salt Lake City and Chicago
B)Salt Lake City and Dallas
C)Chicago and Dallas
D)Dallas
سؤال
The following Maximize: 7X1 + 3X2
Subject to: 5X1 + 7X2 ≤ 27
4X1 + X2 ≤ 14
3X1 - 2X2 ≤ 9
X1, X2 ≥ 0
X1 integer
Represents a:

A)goal programming problem.
B)mixed integer programming problem.
C)nonlinear programming problem.
D)0-1 integer programming problem.
سؤال
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a cost of $2,400 and goal number 2 was to have no idle time for workers in the factory.The optimal solution to this problem resulted in a cost of $2,400 and no idle time.What was the value for the objective function for this goal programming problem?

A)2300
B)100
C)-100
D)0
سؤال
As part of a larger problem, you are trying to determine whether or not to open a plant with a capacity of 10,000 units (using binary variable Y).You also define X as the number of units (if any)produced at that plant.How will you ensure that Y will equal 1 if the plant is open?

A)Y ≥ X
B)Y ≤ X
C)X = 10000Y
D)X ≤ 10000Y
سؤال
If we wish to develop a stock portfolio wherein we maximize return and minimize risk, we would have to use

A)pure-integer programming.
B)goal programming.
C)zero-one integer programming.
D)mixed-integer programming.
سؤال
Agile Bikes has manufacturing plants in Salt Lake City, Dallas, and Chicago.The bikes are shipped to retail stores in Los Angeles, New York, Miami, and Seattle.Information on shipping costs, supply, and demand is given in the following table: <strong>Agile Bikes has manufacturing plants in Salt Lake City, Dallas, and Chicago.The bikes are shipped to retail stores in Los Angeles, New York, Miami, and Seattle.Information on shipping costs, supply, and demand is given in the following table:   What type of mathematical programming is required to solve this problem?</strong> A)linear programming B)integer programming C)mixed-integer programming D)zero-one integer programming <div style=padding-top: 35px> What type of mathematical programming is required to solve this problem?

A)linear programming
B)integer programming
C)mixed-integer programming
D)zero-one integer programming
سؤال
Which of the following statements is false concerning goal programming?

A)The objective function is the main difference between linear programming and goal programming.
B)The objective in goal programming is to minimize deviational variables.
C)Deviational variables are zero if a goal is completely obtained.
D)It is not possible for two goals to have equal priority.
سؤال
Terms that are minimized in goal programming are called

A)deviational variables.
B)global variables.
C)decision variables.
D)minimization variables.
سؤال
What is the optimal solution to the problem described in Table 10-6?

A)X1 = 50; X2 = 0
B)X1 = 30; X2 = 20
C)X1 = 20; X2 = 30
D)X1 = 25; X2 = 25
سؤال
The concept of a local optimum is affiliated with which of the following?

A)mixed integer programming
B)integer programming
C)linear programming
D)nonlinear programming
سؤال
A quadratic programming problem involves which of the following conditions?

A)squared terms in the objective function and linear constraints
B)linear objective function and squared terms in the constraints
C)squared terms in both the objective function and constraints
D)a strictly goal programming problem with squared terms in the objective function
سؤال
Johnny's apple shop sells homemade apple pies and freshly squeezed apple juice.Each apple pie requires 2 apples, and 1 apple yields 4 ounces of juice.Customer's use a self-service dispenser to pour apple juice in a container and are charged by the ounce at a rate of $0.50 per ounce.The contribution to profit of the apple pie, factoring in the apples and remaining ingredients are $2 per pie, and the contribution to profit of freshly squeezed apple juice is $0.20 per ounce.In a given day, there must be at least 100 ounces of apple juice produced and at least 10 apple pies.The company has a supply of 60 apples per day.What is the optimal solution? Apple pies must be produced in whole quantities, but any positive value is positive for juice production.
سؤال
Smalltime Investments Inc.is going to purchase new computers.There are ten employees, and the company would like one for each employee.The cost of the basic personal computer with monitor and disk drive is $2,000, while the deluxe version with VGA and advanced processor is $3,500.Due to internal politics, the number of deluxe computers should be less than half the number of regular computers, but at least three deluxe computers must be purchased.The budget is $27,000, although additional money could be used if it were deemed necessary.All of these are goals that the company has identified.Formulate this as a goal programming problem.
سؤال
Data Equipment Inc.produces two models of a retail price scanner, a sophisticated model that can be networked to a central processing unit and a stand-alone model for small retailers.The major limitations of the manufacturing of these two products are labor and material capacities.The following table summarizes the usages and capacities associated with each product.
Data Equipment Inc.produces two models of a retail price scanner, a sophisticated model that can be networked to a central processing unit and a stand-alone model for small retailers.The major limitations of the manufacturing of these two products are labor and material capacities.The following table summarizes the usages and capacities associated with each product.   The typical LP formulation for this problem is: Maximize $160 X1 + $95 X2 Subject to: 8 X1 + 5 X2 ≤ 800 20 X1 + 7 X2 ≤ 1500 X1, X2 ≥ 0 However, the management of DEI has prioritized several goals that are to be attained by manufacturing: Since the labor situation at the plant is uneasy (i.e., there are rumors that a local union is considering an organizing campaign), management wants to assure full employment of all its employees. Management has established a profit goal of $12,000 per day. Due to the high prices of components from nonroutine suppliers, management wants to minimize the purchase of additional materials. Given the above additional information, set this up as a goal programming problem.<div style=padding-top: 35px>
The typical LP formulation for this problem is:
Maximize $160 X1 + $95 X2
Subject to: 8 X1 + 5 X2 ≤ 800
20 X1 + 7 X2 ≤ 1500
X1, X2 ≥ 0
However, the management of DEI has prioritized several goals that are to be attained by manufacturing:
Since the labor situation at the plant is uneasy (i.e., there are rumors that a local union is considering an organizing campaign), management wants to assure full employment of all its employees.
Management has established a profit goal of $12,000 per day.
Due to the high prices of components from nonroutine suppliers, management wants to minimize the purchase of additional materials.
Given the above additional information, set this up as a goal programming problem.
سؤال
Allied Manufacturing has three factories located in Dallas, Houston, and New Orleans.They each produce the same product and ship to three regional warehouses: #1, #2, and #3.The cost of shipping one unit of each product to each of the three destinations is given below.
Allied Manufacturing has three factories located in Dallas, Houston, and New Orleans.They each produce the same product and ship to three regional warehouses: #1, #2, and #3.The cost of shipping one unit of each product to each of the three destinations is given below.   There is no way to meet the demand for each warehouse.Therefore, the company has decided to set the following goals: (1)the number shipped from each source should be as close to 100 units as possible (overtime may be used if necessary), (2)the number shipped to each destination should be as close to the demand as possible, (3)the total cost should be close to $1,400.Formulate this as a goal programming problem.<div style=padding-top: 35px>
There is no way to meet the demand for each warehouse.Therefore, the company has decided to set the following goals: (1)the number shipped from each source should be as close to 100 units as possible (overtime may be used if necessary), (2)the number shipped to each destination should be as close to the demand as possible, (3)the total cost should be close to $1,400.Formulate this as a goal programming problem.
سؤال
How many constraints are required to develop an integer solution to the haberdashery problem described in Table 10-9?

A)4
B)5
C)6
D)7
سؤال
A package express carrier is considering expanding the fleet of aircraft used to transport packages.Of primary importance is that there is a total of $350 million allocated for purchases.Two types of aircraft may be purchased - the C1A and the C1B.The C1A costs $25 million, while the C1B costs $18 million.The C1A can carry 60,000 pounds of packages, while the C1B can only carry 40,000 pounds of packages.Of secondary importance is that the company needs at least 10 new aircraft.It takes 150 hours per month to maintain the C1A, and 100 hours to maintain the C1B.The least level of importance is that there are a total of 1,200 hours of maintenance time available per month.
(a)First, formulate this as an integer programming problem to maximize the number of pounds that may be carried.
(b)Second, rework the problem differently than in part (a)to suppose the company decides that what is most important to them is that they keep the ratio of C1Bs to C1As in their fleet as close to 1.2 as possible to allow for flexibility in serving their routes.Formulate the goal programming representation of this problem, with the other three goals having priorities P2, P3, and P4, respectively.
سؤال
Johnny's apple shop sells homemade apple pies and freshly squeezed apple juice.Each apple pie requires 2 apples, and 1 apple yields 4 ounces of juice.Customers use a self-service dispenser to pour apple juice in a container and are charged by the ounce at a rate of $0.50 per ounce.The contribution to profit of the apple pie, factoring in the apples and remaining ingredients are $2 per pie, and the contribution to profit of freshly squeezed apple juice is $0.20 per ounce.In a given day, there must be at least 100 ounces of apple juice produced and at least 10 apple pies.The company has a supply of 60 apples per day.Formulate this problem as a mixed integer program.Apple pies must be produced in whole quantities, but any positive value is positive for juice production.
سؤال
Smalltime Investments Inc.is going to purchase new computers for most of the employees.There are ten employees, and at least eight computers must be purchased.The cost of the basic personal computer with monitor and disk drive is $2,000, while the deluxe version with VGA and advanced processor is $3,500.Due to internal politics, the number of deluxe computers must be no more than half the number of regular computers, but at least three deluxe computers must be purchased.The budget is $27,000.Formulate this as an integer programming problem to maximize the number of computers purchased.
سؤال
Data Equipment Inc.produces two models of a retail price scanner, a sophisticated model that can be networked to a central processing unit and a stand-alone model for small retailers.The major limitations of the manufacturing of these two products are labor and material capacities.The following table summarizes the usages and capacities associated with each product.
Data Equipment Inc.produces two models of a retail price scanner, a sophisticated model that can be networked to a central processing unit and a stand-alone model for small retailers.The major limitations of the manufacturing of these two products are labor and material capacities.The following table summarizes the usages and capacities associated with each product.   Capacity 800 hr/day 1,500 comp/day The typical LP formulation for this problem is: Maximize P = $160 X1 + $95 X2 Subject to: 8 X1 + 5 X2 ≤ 800 20 X1 + 7 X2 ≤ 1500 X1, X2 ≥ 0 However, the management of DEI has prioritized several goals that are to be attained by manufacturing: Management had decided to severely limit overtime. Management has established a profit goal of $15,000 per day. Due to the difficulty of obtaining components from non-routine suppliers, management wants to end production with at least 50 units of each component remaining in stock. Management also believes that they should produce at least 30 units of the network model. Given the above additional information, set this up as a goal programming problem.<div style=padding-top: 35px>
Capacity 800 hr/day 1,500 comp/day
The typical LP formulation for this problem is:
Maximize P = $160 X1 + $95 X2
Subject to: 8 X1 + 5 X2 ≤ 800
20 X1 + 7 X2 ≤ 1500
X1, X2 ≥ 0
However, the management of DEI has prioritized several goals that are to be attained by manufacturing:
Management had decided to severely limit overtime.
Management has established a profit goal of $15,000 per day.
Due to the difficulty of obtaining components from non-routine suppliers, management wants to end production with at least 50 units of each component remaining in stock.
Management also believes that they should produce at least 30 units of the network model.
Given the above additional information, set this up as a goal programming problem.
سؤال
Define deviational variables.
سؤال
Define quadratic programming.
سؤال
Bastille College is going to purchase new computers for both faculty and staff.There are a total of 50 people who need new machines - 30 faculty and 20 staff.The cost of the basic personal computer with monitor and disk drive is $2,000, while the deluxe version with VGA and advanced processor is $3,500.Due to internal politics, the number of deluxe computers assigned to staff must be less than half the number of deluxe computers assigned to faculty.The College feels that it must purchase at least 5 deluxe computers for the faculty; if possible, it would like to purchase as many as 20 deluxe computers for the faculty.Staff members do feel somewhat "put upon" by having a limit placed upon the number of deluxe machines purchased for their use, so the College would like to purchase as many deluxe machines for the staff as possible (up to 10).The budget is $100,000.Develop a goal programming formulation of this problem that treats each of the requirements stated above as an equally weighted goal.
سؤال
Allied Manufacturing has three factories located in Dallas, Houston, and New Orleans.They each produce the same 281 products and ship to three regional warehouses - #1, #2, and #3.The cost of shipping one unit of each product to each of the three destinations is given in the table below:
Allied Manufacturing has three factories located in Dallas, Houston, and New Orleans.They each produce the same 281 products and ship to three regional warehouses - #1, #2, and #3.The cost of shipping one unit of each product to each of the three destinations is given in the table below:   There is no way to meet the demand for each warehouse.Therefore, the company has decided to set the following equally weighted goals: (1)each source should ship as much of its capacity as possible, (2)the number shipped to each destination should be as close to the demand as possible, (3)the capacity of New Orleans should be divided as evenly as possible between warehouses #1 and #2, and (4)the total cost should be less than $1,400.Formulate this as a goal program, which includes a strict requirement that capacities cannot be violated.<div style=padding-top: 35px>
There is no way to meet the demand for each warehouse.Therefore, the company has decided to set the following equally weighted goals: (1)each source should ship as much of its capacity as possible, (2)the number shipped to each destination should be as close to the demand as possible, (3)the capacity of New Orleans should be divided as evenly as possible between warehouses #1 and #2, and (4)the total cost should be less than $1,400.Formulate this as a goal program, which includes a strict requirement that capacities cannot be violated.
سؤال
How many constraints are required to develop an integer solution to the haberdashery problem described in Table 10-9?

A)4
B)5
C)6
D)7
سؤال
A package express carrier is considering expanding the fleet of aircraft used to transport packages.There is a total of $220 million allocated for purchases.Two types of aircraft may be purchased - the C1A and the C1B.The C1A costs $25 million, while the C1B costs $18 million.The C1A can carry 60,000 pounds of packages, while the C1B can only carry 40,000 pounds of packages.The company needs at least eight new aircraft.In addition, the firm wishes to purchase at least twice as many C1Bs as C1As.Formulate this as an integer programming problem to maximize the number of pounds that may be carried.
سؤال
The Elastic Firm has two products coming on the market, Zigs and Zags.To make a Zig, the firm needs 10 units of product A and 15 units of product B.To make a Zag, they need 20 units of product A and 15 units of product B.There are only 2,000 units of product A and 3,000 units of product B available to the firm.The profit on a Zig is $4 and on a Zag it is $6.Management objectives in order of their priority are:
(1)Produce at least 40 Zags.
(2)Achieve a target profit of at least $750.
(3)Use all of the product A available.
(4)Use all of the product B available.
(5)Avoid the requirement for more product A.
Formulate this as a goal programming problem.
سؤال
A bakery produces muffins and doughnuts.Let x1 be the number of doughnuts produced and x2 be the number of muffins produced.The profit function for the bakery is expressed by the following equation: profit = 4x1 + 2x2 + 0.3x12 + 0.4x22.The bakery has the capacity to produce 800 units of muffins and doughnuts combined and it takes 30 minutes to produce 100 muffins and 20 minutes to produce 100 doughnuts.There is a total of 4 hours available for baking time.There must be at least 200 units of muffins and at least 200 units of doughnuts produced.Formulate a nonlinear program representing the profit maximization problem for the bakery.
سؤال
Classify the following problems as to whether they are pure-integer, mixed-integer, zero-one, goal, or nonlinear programming problems.
(a)Maximize Z = 5 X1 + 6 X1 X2 + 2 X2
Subject to: 3 X1 + 2 X2 ≥ 6
X1 + X2 ≤ 8
X1, X2 ≥ 0
(b)Minimize Z = 8 X1 + 6 X2
Subject to: 4 X1 + 5 X2 ≥ 10
X1 + X2 ≤ 3
X1, X2 ≥ 0
X1, X2 = 0 or 1
(c)Maximize Z = 10 X1 + 5 X2
Subject to: 8 X1 + 10 X2 = 10
4 X1 + 6 X2 ≥ 5
X1, X2 integer
(d)Minimize Z = 8 X12 + 4 X1 X2 + 12 X22
Subject to: 6 X1 + X2 ≥ 50
X1 + X2 ≥ 40
سؤال
State the advantage of goal programming over linear programming.
سؤال
A bakery produces muffins and doughnuts.Let x1 be the number of doughnuts produced and x2 be the number of muffins produced.The profit function for the bakery is expressed by the following equation: profit = 4x1 + 2x2 + 0.3x12 + 0.4x22.The bakery has the capacity to produce 800 units of muffins and doughnuts combined and it takes 30 minutes to produce 100 muffins and 20 minutes to produce 100 doughnuts.There is a total of 4 hours available for baking time.There must be at least 200 units of muffins and at least 200 units of doughnuts produced.How many doughnuts and muffins should the bakery produce in order to maximize profit?
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/86
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 10: Integer Programming, Goal Programming, and Nonlinear Programming
1
An integer programming solution can never produce a greater profit objective than the LP solution to the same problem.
True
2
A 0-1 programming representation could be used to assign sections of a course to specific classrooms.
True
3
The following objective function is nonlinear: Max 5X - 8YZ.
True
4
In goal programming, the deviational variables have the same objective function coefficients as the surplus and slack variables in a normal linear program.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
5
Nonlinear programming is the case in which objectives and/or constraints are nonlinear.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
6
Unfortunately, multiple goals in goal programming are not able to be prioritized and solved.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
7
There is no general method for solving all nonlinear problems.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
8
The following objective function is nonlinear: Max 5X + (1/8)Y - Z.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
9
In goal programming, if all the goals are achieved, then the value of the objective function will always be zero.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
10
The constraint X1 + X2 ≤ 1 with 0 -1 integer programming allows for either X1 or X2 to be a part of the optimal solution, but not both.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
11
Quadratic programming contains squared terms in the constraints.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
12
The transportation problem is a good example of a pure integer programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
13
The three types of integer programs are: pure integer programming, impure integer programming, and 0-1 integer programming.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
14
Goal programming permits multiple objectives to be satisfied.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
15
Requiring an integer solution to a linear programming problem decreases the size of the feasible region.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
16
If conditions require that all decision variables must have an integer solution, then the class of problem described is an integer programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
17
0-1 integer programming might be applicable to selecting the best gymnastics team to represent a country from among all identified teams.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
18
When solving very large integer programming problems, we sometimes have to settle for a "good," not necessarily optimal, answer.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
19
Unfortunately, goal programming, while able to handle multiple objectives, is unable to prioritize these objectives.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
20
In goal programming, our goal is to drive the deviational variables in the objective function as close to zero as possible.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
21
The global optimum point may be superior to nearby points, but the local optimum point is the true optimal solution-n to a nonlinear programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
22
The constraint X1 - X2 ≤ 0 with 0 -1 integer programming allows for X1 to be selected as part of the optimal solution only if X2 is selected to be a part of the optimal solution, but not both.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
23
An integer programming (maximization)problem was first solved as a linear programming problem, and the objective function value (profit)was $253.67.The two decision variables (X, Y)in the problem had values of X = 12.45 and Y = 32.75.If there is a single optimal solution, which of the following must be true for the optimal integer solution to this problem?

A)X = 12 Y = 32
B)X = 12 Y = 33
C)The objective function value must be less than $253.67.
D)The objective function value will be greater than $253.67.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
24
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a profit of $2,400 and goal number 2 was to have no idle time for workers in the factory.The optimal solution to this problem resulted in a profit of $2,300 and no idle time.What was the value for the objective function for this goal programming problem?

A)2300
B)100
C)-100
D)0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
25
We do not have a general method for solving all types of ________ problems.

A)mixed-integer programming
B)0-1 integer programming
C)goal programming
D)nonlinear programming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
26
A capital budgeting problem involving the selection of possible projects under budget constraints is solved by which of the following?

A)mixed-integer programming
B)0-1 integer programming
C)goal programming
D)nonlinear programming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
27
A mathematical programming model that permits decision makers to set and prioritize multiple objective functions is called a

A)pure-integer programming problem.
B)mixed-integer programming problem.
C)zero-one integer programming problem.
D)goal programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
28
Goal programming differs from linear programming in which of the following aspects?

A)It tries to maximize deviations between set goals and what can be achieved within the constraints.
B)It minimizes instead of maximizing as in LP.
C)It permits multiple goals to be combined into one objective function.
D)It maximizes instead of minimizing as in LP.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
29
The constraint X1 - X2 = 0 with 0 -1 integer programming allows for either both X1 and X2 to be selected to be a part of the optimal solution, or for neither to be selected.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
30
The following objective function is nonlinear: Max 5X + X/Y - Z.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
31
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a profit of $3,600 and goal number 2 was to have no wasted material.The optimal solution to this problem resulted in a profit of $3,300 and no wasted material.What was the value for the objective function for this goal programming problem?

A)300
B)-300
C)3300
D)0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
32
Assignment problems solved previously by linear programming techniques are also examples of

A)pure-integer programming problems.
B)mixed-integer programming problems.
C)zero-one integer programming problems.
D)goal programming problems.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
33
The constraint X1 + X2 + X3+ X4 ≤ 2 with 0 -1 integer programming allows at most two of the items X1, X2, X3, and X4 to be selected to be a part of the optimal solution.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
34
Which of the following is a category of mathematical programming techniques that doesn't assume linearity in the objective function and/or constraints?

A)integer programs
B)goal programming problems
C)nonlinear programs
D)multiple objective programming problems
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
35
In an integer programming problem, if it is desired to have variable X be exactly twice the value of variable Y, the constraint would be written

A)2X + Y = 0.
B)X + 2Y = 0.
C)2X - Y = 0.
D)X - 2Y = 0.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
36
A model containing a linear objective function and linear constraints but requiring that one or more of the decision variables take on an integer value in the final solution is called

A)a goal programming problem.
B)an integer programming problem.
C)a nonlinear programming problem.
D)a multiple objective LP problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
37
In a goal programming problem with two goals at the same priority level, all the deviational variables are equal to zero in the optimal solution.This means

A)there is no feasible solution to the problem.
B)all goals are fully achieved.
C)nonlinear programming must be used to solve this.
D)this problem was an integer programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
38
An integer programming (minimization)problem was first solved as a linear programming problem, and the objective function value (cost)was $253.67.The two decision variables (X, Y)in the problem had values of X = 12.45 and Y = 32.75.If there is a single optimal solution, which of the following must be true for the optimal integer solution to this problem?

A)X = 13 Y = 33
B)X = 12 Y = 32
C)The objective function value must be less than $253.67.
D)The objective function value will be greater than $253.67.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
39
Goal programming is characterized by

A)all maximization problems.
B)setting of lower and upper bounds.
C)the deviation from a high-priority goal must be minimized before the next-highest-priority goal may be considered.
D)deviation from certainty.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
40
Which of the following functions is nonlinear?

A)4X + 2Y + 7Z
B)-4X + 2Y
C)4X + (1/2)Y + 7Z
D)4X/Y + 7Z
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
41
Consider the following 0-1 integer programming problem: Minimize 20X + 36Y +24Z
Subject to: 2X + 4Y + 3Z ≥ 7
12X + 8Y + 10Z ≥ 25
X, Y, Z must be 0 or 1
If we wish to add the constraint that no more than two of these variables must be positive, how would this be written?

A)2X + 2Y + 2Z ≤ 3
B)X + Y + Z ≤ 2
C)X ≤ 2, and Y ≤ 2, and Z ≤ 2
D)X, Y, Z ≤ 2
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
42
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a cost of $3,600 and goal number 2 was to have no wasted material.The optimal solution to this problem resulted in a cost of $3,900 and no wasted material.What was the value for the objective function for this goal programming problem?

A)300
B)-300
C)3300
D)0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
43
The overall best solution in a nonlinear program is a

A)global optimum.
B)local optimum.
C)binary optimum.
D)nonlinear optimum.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
44
Which of the following is not considered nonlinear programming?

A)nonlinear objective and nonlinear constraints
B)nonlinear objective with linear constraints
C)binary decision variable with nonlinear constraints
D)integer decision variable with linear constraints
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
45
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a cost of $3,600 and goal number 2 was to complete the task in 400 hours or fewer.The optimal solution to this problem resulted in a cost of $3,600 and a completion time of 420 hours.What was the value for the objective function for this goal programming problem?

A)400
B)-400
C)20
D)0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
46
Consider the following 0-1 integer programming problem: Minimize 20X + 36Y + 24Z
Subject to: 2X + 4Y + 3Z ≥ 7
12X + 8Y + 10Z ≥ 25
X, Y, Z must be 0 or 1
If we wish to add the constraint that X must be positive, and that only Y or Z, but not both, can be positive, how would the additional constraint(s)be written?

A)X + Y + Z ≤ 3, Y + Z ≤ 1
B)X ≤ 1, Y + Z = 1
C)X ≤ 2, and Y ≤ 2, and Z ≤ 2
D)X = 1, Y + Z ≤ 1
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
47
Another name for a 0-1 variable is a(n)________ variable.

A)either-or
B)binary
C)yes-no
D)quadratic
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
48
A transportation problem is an example of

A)a pure-integer programming problem.
B)a mixed-integer programming problem.
C)a zero-one integer programming problem.
D)a goal programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
49
The concept of "satisficing" is affiliated with which of the following?

A)mixed integer programming
B)integer programming
C)nonlinear programming
D)goal programming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
50
Agile Bikes has manufacturing plants in Salt Lake City, Dallas, and Chicago.The bikes are shipped to retail stores in Los Angeles, New York, Miami, and Seattle.Information on shipping costs, supply, and demand is given in the following table: <strong>Agile Bikes has manufacturing plants in Salt Lake City, Dallas, and Chicago.The bikes are shipped to retail stores in Los Angeles, New York, Miami, and Seattle.Information on shipping costs, supply, and demand is given in the following table:   Where should Los Angeles receive their bicycles from?</strong> A)Salt Lake City and Chicago B)Salt Lake City and Dallas C)Chicago and Dallas D)Dallas Where should Los Angeles receive their bicycles from?

A)Salt Lake City and Chicago
B)Salt Lake City and Dallas
C)Chicago and Dallas
D)Dallas
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
51
The following Maximize: 7X1 + 3X2
Subject to: 5X1 + 7X2 ≤ 27
4X1 + X2 ≤ 14
3X1 - 2X2 ≤ 9
X1, X2 ≥ 0
X1 integer
Represents a:

A)goal programming problem.
B)mixed integer programming problem.
C)nonlinear programming problem.
D)0-1 integer programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
52
A goal programming problem had two goals (with no priorities assigned).Goal number 1 was to achieve a cost of $2,400 and goal number 2 was to have no idle time for workers in the factory.The optimal solution to this problem resulted in a cost of $2,400 and no idle time.What was the value for the objective function for this goal programming problem?

A)2300
B)100
C)-100
D)0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
53
As part of a larger problem, you are trying to determine whether or not to open a plant with a capacity of 10,000 units (using binary variable Y).You also define X as the number of units (if any)produced at that plant.How will you ensure that Y will equal 1 if the plant is open?

A)Y ≥ X
B)Y ≤ X
C)X = 10000Y
D)X ≤ 10000Y
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
54
If we wish to develop a stock portfolio wherein we maximize return and minimize risk, we would have to use

A)pure-integer programming.
B)goal programming.
C)zero-one integer programming.
D)mixed-integer programming.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
55
Agile Bikes has manufacturing plants in Salt Lake City, Dallas, and Chicago.The bikes are shipped to retail stores in Los Angeles, New York, Miami, and Seattle.Information on shipping costs, supply, and demand is given in the following table: <strong>Agile Bikes has manufacturing plants in Salt Lake City, Dallas, and Chicago.The bikes are shipped to retail stores in Los Angeles, New York, Miami, and Seattle.Information on shipping costs, supply, and demand is given in the following table:   What type of mathematical programming is required to solve this problem?</strong> A)linear programming B)integer programming C)mixed-integer programming D)zero-one integer programming What type of mathematical programming is required to solve this problem?

A)linear programming
B)integer programming
C)mixed-integer programming
D)zero-one integer programming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
56
Which of the following statements is false concerning goal programming?

A)The objective function is the main difference between linear programming and goal programming.
B)The objective in goal programming is to minimize deviational variables.
C)Deviational variables are zero if a goal is completely obtained.
D)It is not possible for two goals to have equal priority.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
57
Terms that are minimized in goal programming are called

A)deviational variables.
B)global variables.
C)decision variables.
D)minimization variables.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
58
What is the optimal solution to the problem described in Table 10-6?

A)X1 = 50; X2 = 0
B)X1 = 30; X2 = 20
C)X1 = 20; X2 = 30
D)X1 = 25; X2 = 25
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
59
The concept of a local optimum is affiliated with which of the following?

A)mixed integer programming
B)integer programming
C)linear programming
D)nonlinear programming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
60
A quadratic programming problem involves which of the following conditions?

A)squared terms in the objective function and linear constraints
B)linear objective function and squared terms in the constraints
C)squared terms in both the objective function and constraints
D)a strictly goal programming problem with squared terms in the objective function
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
61
Johnny's apple shop sells homemade apple pies and freshly squeezed apple juice.Each apple pie requires 2 apples, and 1 apple yields 4 ounces of juice.Customer's use a self-service dispenser to pour apple juice in a container and are charged by the ounce at a rate of $0.50 per ounce.The contribution to profit of the apple pie, factoring in the apples and remaining ingredients are $2 per pie, and the contribution to profit of freshly squeezed apple juice is $0.20 per ounce.In a given day, there must be at least 100 ounces of apple juice produced and at least 10 apple pies.The company has a supply of 60 apples per day.What is the optimal solution? Apple pies must be produced in whole quantities, but any positive value is positive for juice production.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
62
Smalltime Investments Inc.is going to purchase new computers.There are ten employees, and the company would like one for each employee.The cost of the basic personal computer with monitor and disk drive is $2,000, while the deluxe version with VGA and advanced processor is $3,500.Due to internal politics, the number of deluxe computers should be less than half the number of regular computers, but at least three deluxe computers must be purchased.The budget is $27,000, although additional money could be used if it were deemed necessary.All of these are goals that the company has identified.Formulate this as a goal programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
63
Data Equipment Inc.produces two models of a retail price scanner, a sophisticated model that can be networked to a central processing unit and a stand-alone model for small retailers.The major limitations of the manufacturing of these two products are labor and material capacities.The following table summarizes the usages and capacities associated with each product.
Data Equipment Inc.produces two models of a retail price scanner, a sophisticated model that can be networked to a central processing unit and a stand-alone model for small retailers.The major limitations of the manufacturing of these two products are labor and material capacities.The following table summarizes the usages and capacities associated with each product.   The typical LP formulation for this problem is: Maximize $160 X1 + $95 X2 Subject to: 8 X1 + 5 X2 ≤ 800 20 X1 + 7 X2 ≤ 1500 X1, X2 ≥ 0 However, the management of DEI has prioritized several goals that are to be attained by manufacturing: Since the labor situation at the plant is uneasy (i.e., there are rumors that a local union is considering an organizing campaign), management wants to assure full employment of all its employees. Management has established a profit goal of $12,000 per day. Due to the high prices of components from nonroutine suppliers, management wants to minimize the purchase of additional materials. Given the above additional information, set this up as a goal programming problem.
The typical LP formulation for this problem is:
Maximize $160 X1 + $95 X2
Subject to: 8 X1 + 5 X2 ≤ 800
20 X1 + 7 X2 ≤ 1500
X1, X2 ≥ 0
However, the management of DEI has prioritized several goals that are to be attained by manufacturing:
Since the labor situation at the plant is uneasy (i.e., there are rumors that a local union is considering an organizing campaign), management wants to assure full employment of all its employees.
Management has established a profit goal of $12,000 per day.
Due to the high prices of components from nonroutine suppliers, management wants to minimize the purchase of additional materials.
Given the above additional information, set this up as a goal programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
64
Allied Manufacturing has three factories located in Dallas, Houston, and New Orleans.They each produce the same product and ship to three regional warehouses: #1, #2, and #3.The cost of shipping one unit of each product to each of the three destinations is given below.
Allied Manufacturing has three factories located in Dallas, Houston, and New Orleans.They each produce the same product and ship to three regional warehouses: #1, #2, and #3.The cost of shipping one unit of each product to each of the three destinations is given below.   There is no way to meet the demand for each warehouse.Therefore, the company has decided to set the following goals: (1)the number shipped from each source should be as close to 100 units as possible (overtime may be used if necessary), (2)the number shipped to each destination should be as close to the demand as possible, (3)the total cost should be close to $1,400.Formulate this as a goal programming problem.
There is no way to meet the demand for each warehouse.Therefore, the company has decided to set the following goals: (1)the number shipped from each source should be as close to 100 units as possible (overtime may be used if necessary), (2)the number shipped to each destination should be as close to the demand as possible, (3)the total cost should be close to $1,400.Formulate this as a goal programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
65
How many constraints are required to develop an integer solution to the haberdashery problem described in Table 10-9?

A)4
B)5
C)6
D)7
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
66
A package express carrier is considering expanding the fleet of aircraft used to transport packages.Of primary importance is that there is a total of $350 million allocated for purchases.Two types of aircraft may be purchased - the C1A and the C1B.The C1A costs $25 million, while the C1B costs $18 million.The C1A can carry 60,000 pounds of packages, while the C1B can only carry 40,000 pounds of packages.Of secondary importance is that the company needs at least 10 new aircraft.It takes 150 hours per month to maintain the C1A, and 100 hours to maintain the C1B.The least level of importance is that there are a total of 1,200 hours of maintenance time available per month.
(a)First, formulate this as an integer programming problem to maximize the number of pounds that may be carried.
(b)Second, rework the problem differently than in part (a)to suppose the company decides that what is most important to them is that they keep the ratio of C1Bs to C1As in their fleet as close to 1.2 as possible to allow for flexibility in serving their routes.Formulate the goal programming representation of this problem, with the other three goals having priorities P2, P3, and P4, respectively.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
67
Johnny's apple shop sells homemade apple pies and freshly squeezed apple juice.Each apple pie requires 2 apples, and 1 apple yields 4 ounces of juice.Customers use a self-service dispenser to pour apple juice in a container and are charged by the ounce at a rate of $0.50 per ounce.The contribution to profit of the apple pie, factoring in the apples and remaining ingredients are $2 per pie, and the contribution to profit of freshly squeezed apple juice is $0.20 per ounce.In a given day, there must be at least 100 ounces of apple juice produced and at least 10 apple pies.The company has a supply of 60 apples per day.Formulate this problem as a mixed integer program.Apple pies must be produced in whole quantities, but any positive value is positive for juice production.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
68
Smalltime Investments Inc.is going to purchase new computers for most of the employees.There are ten employees, and at least eight computers must be purchased.The cost of the basic personal computer with monitor and disk drive is $2,000, while the deluxe version with VGA and advanced processor is $3,500.Due to internal politics, the number of deluxe computers must be no more than half the number of regular computers, but at least three deluxe computers must be purchased.The budget is $27,000.Formulate this as an integer programming problem to maximize the number of computers purchased.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
69
Data Equipment Inc.produces two models of a retail price scanner, a sophisticated model that can be networked to a central processing unit and a stand-alone model for small retailers.The major limitations of the manufacturing of these two products are labor and material capacities.The following table summarizes the usages and capacities associated with each product.
Data Equipment Inc.produces two models of a retail price scanner, a sophisticated model that can be networked to a central processing unit and a stand-alone model for small retailers.The major limitations of the manufacturing of these two products are labor and material capacities.The following table summarizes the usages and capacities associated with each product.   Capacity 800 hr/day 1,500 comp/day The typical LP formulation for this problem is: Maximize P = $160 X1 + $95 X2 Subject to: 8 X1 + 5 X2 ≤ 800 20 X1 + 7 X2 ≤ 1500 X1, X2 ≥ 0 However, the management of DEI has prioritized several goals that are to be attained by manufacturing: Management had decided to severely limit overtime. Management has established a profit goal of $15,000 per day. Due to the difficulty of obtaining components from non-routine suppliers, management wants to end production with at least 50 units of each component remaining in stock. Management also believes that they should produce at least 30 units of the network model. Given the above additional information, set this up as a goal programming problem.
Capacity 800 hr/day 1,500 comp/day
The typical LP formulation for this problem is:
Maximize P = $160 X1 + $95 X2
Subject to: 8 X1 + 5 X2 ≤ 800
20 X1 + 7 X2 ≤ 1500
X1, X2 ≥ 0
However, the management of DEI has prioritized several goals that are to be attained by manufacturing:
Management had decided to severely limit overtime.
Management has established a profit goal of $15,000 per day.
Due to the difficulty of obtaining components from non-routine suppliers, management wants to end production with at least 50 units of each component remaining in stock.
Management also believes that they should produce at least 30 units of the network model.
Given the above additional information, set this up as a goal programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
70
Define deviational variables.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
71
Define quadratic programming.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
72
Bastille College is going to purchase new computers for both faculty and staff.There are a total of 50 people who need new machines - 30 faculty and 20 staff.The cost of the basic personal computer with monitor and disk drive is $2,000, while the deluxe version with VGA and advanced processor is $3,500.Due to internal politics, the number of deluxe computers assigned to staff must be less than half the number of deluxe computers assigned to faculty.The College feels that it must purchase at least 5 deluxe computers for the faculty; if possible, it would like to purchase as many as 20 deluxe computers for the faculty.Staff members do feel somewhat "put upon" by having a limit placed upon the number of deluxe machines purchased for their use, so the College would like to purchase as many deluxe machines for the staff as possible (up to 10).The budget is $100,000.Develop a goal programming formulation of this problem that treats each of the requirements stated above as an equally weighted goal.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
73
Allied Manufacturing has three factories located in Dallas, Houston, and New Orleans.They each produce the same 281 products and ship to three regional warehouses - #1, #2, and #3.The cost of shipping one unit of each product to each of the three destinations is given in the table below:
Allied Manufacturing has three factories located in Dallas, Houston, and New Orleans.They each produce the same 281 products and ship to three regional warehouses - #1, #2, and #3.The cost of shipping one unit of each product to each of the three destinations is given in the table below:   There is no way to meet the demand for each warehouse.Therefore, the company has decided to set the following equally weighted goals: (1)each source should ship as much of its capacity as possible, (2)the number shipped to each destination should be as close to the demand as possible, (3)the capacity of New Orleans should be divided as evenly as possible between warehouses #1 and #2, and (4)the total cost should be less than $1,400.Formulate this as a goal program, which includes a strict requirement that capacities cannot be violated.
There is no way to meet the demand for each warehouse.Therefore, the company has decided to set the following equally weighted goals: (1)each source should ship as much of its capacity as possible, (2)the number shipped to each destination should be as close to the demand as possible, (3)the capacity of New Orleans should be divided as evenly as possible between warehouses #1 and #2, and (4)the total cost should be less than $1,400.Formulate this as a goal program, which includes a strict requirement that capacities cannot be violated.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
74
How many constraints are required to develop an integer solution to the haberdashery problem described in Table 10-9?

A)4
B)5
C)6
D)7
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
75
A package express carrier is considering expanding the fleet of aircraft used to transport packages.There is a total of $220 million allocated for purchases.Two types of aircraft may be purchased - the C1A and the C1B.The C1A costs $25 million, while the C1B costs $18 million.The C1A can carry 60,000 pounds of packages, while the C1B can only carry 40,000 pounds of packages.The company needs at least eight new aircraft.In addition, the firm wishes to purchase at least twice as many C1Bs as C1As.Formulate this as an integer programming problem to maximize the number of pounds that may be carried.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
76
The Elastic Firm has two products coming on the market, Zigs and Zags.To make a Zig, the firm needs 10 units of product A and 15 units of product B.To make a Zag, they need 20 units of product A and 15 units of product B.There are only 2,000 units of product A and 3,000 units of product B available to the firm.The profit on a Zig is $4 and on a Zag it is $6.Management objectives in order of their priority are:
(1)Produce at least 40 Zags.
(2)Achieve a target profit of at least $750.
(3)Use all of the product A available.
(4)Use all of the product B available.
(5)Avoid the requirement for more product A.
Formulate this as a goal programming problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
77
A bakery produces muffins and doughnuts.Let x1 be the number of doughnuts produced and x2 be the number of muffins produced.The profit function for the bakery is expressed by the following equation: profit = 4x1 + 2x2 + 0.3x12 + 0.4x22.The bakery has the capacity to produce 800 units of muffins and doughnuts combined and it takes 30 minutes to produce 100 muffins and 20 minutes to produce 100 doughnuts.There is a total of 4 hours available for baking time.There must be at least 200 units of muffins and at least 200 units of doughnuts produced.Formulate a nonlinear program representing the profit maximization problem for the bakery.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
78
Classify the following problems as to whether they are pure-integer, mixed-integer, zero-one, goal, or nonlinear programming problems.
(a)Maximize Z = 5 X1 + 6 X1 X2 + 2 X2
Subject to: 3 X1 + 2 X2 ≥ 6
X1 + X2 ≤ 8
X1, X2 ≥ 0
(b)Minimize Z = 8 X1 + 6 X2
Subject to: 4 X1 + 5 X2 ≥ 10
X1 + X2 ≤ 3
X1, X2 ≥ 0
X1, X2 = 0 or 1
(c)Maximize Z = 10 X1 + 5 X2
Subject to: 8 X1 + 10 X2 = 10
4 X1 + 6 X2 ≥ 5
X1, X2 integer
(d)Minimize Z = 8 X12 + 4 X1 X2 + 12 X22
Subject to: 6 X1 + X2 ≥ 50
X1 + X2 ≥ 40
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
79
State the advantage of goal programming over linear programming.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
80
A bakery produces muffins and doughnuts.Let x1 be the number of doughnuts produced and x2 be the number of muffins produced.The profit function for the bakery is expressed by the following equation: profit = 4x1 + 2x2 + 0.3x12 + 0.4x22.The bakery has the capacity to produce 800 units of muffins and doughnuts combined and it takes 30 minutes to produce 100 muffins and 20 minutes to produce 100 doughnuts.There is a total of 4 hours available for baking time.There must be at least 200 units of muffins and at least 200 units of doughnuts produced.How many doughnuts and muffins should the bakery produce in order to maximize profit?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 86 في هذه المجموعة.